3.0 Specific Reclamation Activities and Results <br />3.1 Phase I Areas <br />As shown on Exhibit 1, each area requested for bond release is comprised of smaller <br />units, which correspond to the specific year that backfilling and grading was <br />performed. The work completed includes regrading to the approved post- mining <br />topography and installation of post- mining drainage channels in required areas. <br />Grading and topsoil replacement is generally performed in the summer and fall <br />months. See Table 1- Summary of Reclamation Activities for an overview of the <br />worked performed for each reclaimed area. <br />The reclaimed areas have been regraded consistent with the approved post- mining <br />topography (See Map 19 and 19A, Permit C -81 -019 for the approved post- mining <br />topography) and follow all criteria set forth for Phase I bond release by the Division. <br />Please refer to Exhibit 2A and 2B for five (5) representative cross - sections of the <br />regraded areas in relation to the approved post- mining topography. The cross - <br />sections indicate that the Phase I areas fall within the Division's guidelines of a <br />maximum variance of 1 /2 of a contour from the approved post- mining topography and <br />are well within acceptable mining practice. <br />Permanent and temporary channels have been established in the Phase I areas, in <br />accordance with the approved construction design parameters located in Permit C- <br />81 -019. These constructed channels including locations and cross - section are <br />identified in the 2012 Annual Reclamation Report on file at the Colowyo Mine site <br />and the Colorado Division of Reclamation Mining and Safety Denver office. This <br />document is available for review upon request. <br />