Laserfiche WebLink
cc <br />&v <br />amee <br />Tree /Slash Clearing, Chipping: <br />Seed Masters continues to 'grind and chip' stockpiled trees and brush within the ADR, east of HWY 67 left of the <br />ADR haul road. Equipment (Seed Masters): one "Chipper, one CAT 330 Excavator <br />B) Underground Workings <br />During the reporting period exploratory excavation and remediation were performed on UG Working No. 6038, No. <br />6039, No. 6040, No. 6041, No 6042, No. 6043, No. 6044, No 6045 and No. 6056. The sites were excavated to <br />practical refusal into rock to a depth of 9 feet to 20 feet. The site for each working was then backfilled in 2 foot loose <br />lifts to approximate planned subgrade elevation using the onsite structural fill (excavated material) and 'bucket <br />tamped" with the back of the CAT 330 excavator bucket. All backfill material was free of organic material, ice and <br />snow. <br />UG #6037: Exploratory findings indicate this is a collapsed shaft. Timbers were observed and removed from 12 <br />feet to 22 +1- feet. Confirmatory drilling was performed. 31 drilling locations were established encompassing UG <br />#6037. All locations were placed on 4 foot centers. Confirmatory drilling commenced using one Sandvek 800 track <br />drill rig and one Sandvek 700 track drill rig. Work will continue to encompass the working and to locate and isolate <br />the void found. <br />UG #6051 (Historical #55): Visual findings indicate the working is a timbered shaft estimated to be 10 feet in length <br />by 5 feet in width. Confirmatory drilling was performed. A total of 23 drilling locations were established and placed <br />on approximate 4 foot centers. 9 drill locations were completed to 50 and 51 feet. Voids were found in 3 drill <br />locations ranging in depth from 43.5 to 45 feet and extending to a depth of 50 to 51 feet. Work will continue on the <br />remaining drill locations and additional drill locations will be established to further investigate and isolate the void. <br />During the reporting period, Underground working No. 6018 was blasted for further exploratory investigation. <br />Underground working delineation drilling and investigations and remediation continue. <br />C) Highway 67 <br />MHT #2 is in place and is working properly. No other work was performed for the existing HWY 67 crossing during <br />this reporting period. <br />II) Storm Water Management <br />A) Best Management Practices (BMP) are being performed. Inspections continue and there have been no <br />issues identified. <br />CQA ACTIVITIES: <br />I) Field Activities: Construction activities and observation of clearing and grubbing, structural fill and compaction, <br />underground workings, HWY 67 progress observation were some of the tasks performed in the field as required to <br />project specifications.. <br />II) Laboratory Activities: Laboratory testing continued (Particle Size Distribution, Atterberg Limits, Moisture- Density, <br />gradations and material identifications) were some of the laboratory testing performed during this reporting period as <br />required to project specifications. <br />Page 2 of 6 MLE2 WE 03.02.13.doc <br />