9 }
<br /> sheet 7 of 8
<br /> STRUCTURAL DEMOLITION WORK cont'd
<br /> --------------------------
<br /> MEANS BASE TOTAL
<br /> STRUCTURE / FACILITY / EQUIPMENT DESCRIPTION DIMENSIONS COMPOSITION QUANTITY UNIT UNIT COST COST ($)
<br /> MET LAB - SUPERSTRUCTURE 32'L X 44'W X 10'H STEEL 14,080 CU.FT. $0.18 $2,674
<br /> FLOOR (811T w/wire mesh) 32'L X 44'W CONCRETE 1,408 SQ.FT. $3.55 $5,273
<br /> " - FOOTING (1.5' X 2.0') 32'+32'+44'+44' CONCRETE I 152 I LIN.FT. I $10.45 I $1,676
<br /> ASBESTOS REMOVAL I NA I ASBESTOS I 1 I ESTIMATI $6,696.00 I $7,064
<br /> 2 CR DUST COLLECTOR- SUPERSTRUCTURE I 741L X 36'W X 30'H I STEEL 79,920 CU.FT. $0.18 $15,177
<br /> FLOOR (10"T w/rebar) I 74'L X 361W I CONCRETE 2,664 SQ.FT. I $4.73 $13,294
<br /> FOOTING (1.5'T X 2.0'W) I 74'+74'+36'+36' I CONCRETE 220 I LIN.FT.I $10.45 I $2,425
<br /> " - ASBESTOS REMOVAL I NA I ASBESTOS 1 1 I ESTIMATI $8,460.00 I $8,925
<br /> COV STORAGE LINE CRW- SUPERSTRUCTURE 35'L X 55'W X 14'H TIN 26,950 CU.FT. ( $0.18 $5,118
<br /> FLOOR (811T plain) 35'L X 551W CONCRETE 1,925 SQ.FT. $3.16 $6,418
<br /> FOOTING (1.5'T X 2.01W) 35'+35'+55'+55' CONCRETE 180 I LIN.FT.I $9.50 I $1,804
<br /> ASBESTOS REMOVAL NA ASBESTOS 1 I ESTIMATI **********I $19,283
<br /> SCALE HOUSE - SUPERSTRUCTURE 80'L X 161W X 16'H STEEL 20,480 CU.FT. $0.18 $3,889
<br /> " - FLOOR (10"T plain) 80'L X 16'W CONCRETE 1,280 SQ.FT. $3.80 $5,132
<br /> - FOOTING (1.5'T X 2.01W) 80'+80'+16'+16' CONCRETE 192 I LIN.FT.I $9.50 I $1,924
<br /> P2S5 BUILDING - SUPERSTRUCTURE I 65'L X 35'W X 16'H I STEEL 36,400 CU.FT. $0.18 $6,912
<br /> " - FLOOR (811T w/rebar) 65'L X 35'W I CONCRETE 2,275 SQ.FT. $3.94 $9,456
<br /> - FOOTING (1.51T X 2.01W) 65'+65'+35'+35' CONCRETE 200 I LIN.FT.I $10.45 I $2,205
<br /> 45 DRIVE BUILDING - SUPERSTRUCTURE 110'L X 521W X 40'H STEEL 228,800 CU.FT. $0.18 $43,449
<br /> - FLOOR (12"T w/rebar) 1101L X 521W X 401H CONCRETE 5,720 SQ.FT. $5.52 $33,311
<br /> " - FOOTING (2.0'T X 3.01W) 110'+110'+52'+52' CONCRETE 324 I LIN.FT.I $16.26 I $5,558
<br /> 20 K BIN - SUPERSTRUCTURE 220'L X 117'W X 40'H I STEEL I1,029,600 I CU.FT. I $0.18 I $195,521
<br /> - FLOOR (12"T w/rebar) 220'L X 1171W CONCRETE 25,740 I SQ.FT. I $5.52 I $149,899
<br /> - FOOTING (2.0'T X 3.01W) 220'+220'+117'+117' CONCRETE 674 I LIN.FT.I $16.26 I $11,562
<br /> - ASBESTOS REMOVAL NA ASBESTOS I 1 I ESTIMATI **********I $22,232
<br /> 29A/30 TRANS TOWER - SUPERSTRUCTURE 26'L X 261W X 401H STEEL 27,040 CU.FT. $0.18 $5,135
<br /> " - FLOOR (8"T w/rebar) 26'L X 26'W CONCRETE 676 SQ.FT. $3.94 $2,810
<br /> - FOOTING (1.51T X 2.01W) 26'+26'+26'+26' CONCRETE 104 I LIN.FT. I $10.45 I $1,147
<br /> - ASBESTOS REMOVAL I NA I ASBESTOS I 1 I ESTIMATI $4,063.00 I $4,286
<br /> NO 28 ROTOCLONE - SUPERSTRUCTURE I 17'L X 41'W X 16'H I STEEL 11,152 I CU.FT. $0.18 I $2,118
<br /> - FLOOR (8"T w/rebar) I 17'L X 41'W I CONCRETE 697 SQ.FT. $3.94 I $2,897
<br /> - FOOTING (1.5'T X 2.01W) 17'+17'+41'+41' CONCRETE I 116 I LIN.FT. I $10.45 1 $1,279
<br /> 48 ROTOCLONE - SUPERSTRUCTURE 51'L X 511W X 261H STEEL 67,626 I CU.FT. $0.18 i $12,842
<br /> - FLOOR (8"T w/rebar) 51'L X 511W I CONCRETE 2,601 I SQ.FT. $3.94 I $10,812
<br /> " - FOOTING (1.5'T X 2.0'W) 51'+51'+51'+51' CONCRETE 204 I LIN.FT. I $10.45 I $2,249
<br /> - ASBESTOS REMOVAL I NA I ASBESTOS 1 1 I ESTIMATI $1,616.00 I $1,705
<br /> PHLLPSN MAPP GAS HSE- SUPERSTRUCTURE I 20'L X 45'W X 8'H I TIN 7,200 I CU.FT. $0.18 $1,367
<br /> FLOOR (811T plain) 2011, X 45'W I CONCRETE 900 I SQ.FT. $3.16 $3,000
<br /> FOOTING (1.5'T X 2.01W) I 20'+20'+45'+45' I CONCRETE 1 130 I LIN.FT. I $9.50 I $1,303
<br /> OPEN PIT FUEL TANKS - SUPERSTRUCTURE I 100'L X 25'W X 8'H STEEL 20,000 I CU.FT. $0.18 $3,798
<br /> " - FLOOR (811T plain) I 100'L X 25'W CONCRETE 2,500 I SQ.FT. $3.16 $8,335
<br /> - FOOTING (1.5'T X 2.01W) I 100'+100'+25'+25' I CONCRETE 250 I LIN.FT. I $9.50 I $2,506
<br /> SHOVEL REBUILD SHOP - SUPERSTRUCTURE I 150'L X 15'W X 15'H I STEEL 33,750 CU.FT. I $0.18 I $6,409
<br /> " - FLOOR (10"T plain) I 150'L X 15'W I CONCRETE 2,250 I SQ.FT. I $3.80 I $9,020
<br /> " - FOOTING (1.5'T X 2.01W) 150'+150'+15'+15' I CONCRETE 1 330 I LIN.FT. I $9.50 I $3,307
<br /> OPEN PIT PWDR MAGS - SUPERSTRUCTURE 150'L X 15'W X 15'H STEEL 33,750 I CU.FT. $0.18 $6,409
<br /> - FLOOR (10"T plain) I 1501L X 151W CONCRETE 2,250 I SQ.FT. $3.80 $9,020
<br /> - FOOTING (1.5'T X 2.01W) I 150'+150'+15'+15' CONCRETE I 330 I LIN.FT. I $9.50 I $3,307
<br /> I I I I I
<br /> I I I 1
<br /> TASK SUBTOTAL - sheet 7 $685,244
<br />
|