i
<br /> i
<br /> sheet 5 of 8
<br /> STRUCTURAL DEMOLITION WORK cont-d
<br /> I I I I I MEANS BASEI� .TOTAL
<br /> STRUCTURE / FACILITY / EQUIPMENT DESCRIPTION I DIMENSIONS I COMPOSITION I QUANTITY I UNIT I UNIT COST I COST (S)
<br /> - ---- ------- ---- - - ----
<br /> Shop Area Concrete Removal, continued
<br /> I I I I I I
<br /> Offices i 92' X 183' I concrete I 16,836 I sq.ft. I $2.78 I $46,664
<br /> Ambulance Garage 170' X 76, I concrete ( 5,320 I sq.ft. I $2.78 I $14,745
<br /> Cylinder Storage , 114' X 16' I concrete I 224 I sq.ft. I $2.78 I 5621
<br /> Warehouse 170, X 160, I concrete I 11,200 ( sq.ft. I $2.78 I 531,043
<br /> Warehouse 180' X 120' I concrete I 9,600 I sq.ft. I $2.78 I $26,608
<br /> Bus Garage 170' X 801 I concrete I 5,600 I sq.ft. I $2.78 I 515,521
<br /> Water Storage I Perimeter of 481 d. I concrete I 151 1 lin.ft.I 57.87 I $1,183
<br /> Dutch Creek Flume, sides 12 - 41 X 5001 ; 8" I concrete I 4,000 I sq.ft. I $8.11 I $32,343
<br /> Dutch Creek Flume, bottom 112' X 500' 1211 I concrete I 6,000 I sq.ft. I $7.39 I $44,207
<br /> Retaining Wall at Substation/Conveyor 1101 X 30, 84- I concrete I 300 I sq.ft. ( 58.11 I $2,426
<br /> I I I I I I
<br /> PREPARATION PLANT AREA I I I I I I
<br /> I I I I I I
<br /> Conveyor to Old Refuse Pile I - 800' I steel i 800 I lin.ft.I $25.00 I 519,940
<br /> Interplant Conveyors ( 36-- - 200, I steel I 200 I Lin.ft.I $25.00 I $4,985
<br /> Conveyor Transfer Buildings 14(15' X 15, 151) I steel I 13,500 I cu.ft. I SO.17 I $2,288
<br /> Prep Plant 192, X 225, X 50, I steel I1,035,000 I cu.ft. I $0.17 I $175,422
<br /> Thermal Dryer #1 142, X 74, X 50, i steel I 155,400 I cu.ft. I $0.17 I $26,339
<br /> Thermal Dryer #2 142, X 741 X 501 ( steel I 155,400 I cu.ft. I SO.17 I 526,339
<br /> Shop ( 40, X 50' X 10, I steel I 20,000 I cu.ft. I $0.17 I 53,390
<br /> Crusher 122' X 54' X 10, I steel I 11,880 I cu.ft. I $0.17 ( $2,014
<br /> Clean Coal Storage Bin 1321 d. - 50' I steel I 40,212 I cu.ft. I SO.17 I $6,816
<br /> 'Lean Coal Storage Bin 132' d. - 50' I steel ( 40,212 I cu.ft. I $0.17 ( $6,816
<br /> Aorage Bin 132' d. - 50, I steel I 40,212 I cu.ft. I SO.17 I $6,816
<br /> Raw Coat Storage Bin i 32, d. - 50, I steel I 40,212 I cu.ft. I SO.17 I $6,816
<br /> Raw Coal Storage Sin 132, d. - 50, I steel I 40,212 I cu.ft. I SO.17 I 56,816
<br /> Powder Magazines - 2 12(8' X 121 X 101) I cin blk I 1,920 I cu.ft. I $0.17 I S325
<br /> Powder Magazine 113, X 241 X 10, I cin blk I 3,120 I cu.ft. I 50.17 I 5529
<br /> I I I I I I
<br /> Concrete Removal
<br /> I I I I I I
<br /> Conveyor Supports - 401 interval 140 - 2' X 21 X 31 I concrete I 80 I lin.ft.I $13.50 I 51,077
<br /> Transfer Buildings - 4 116 - 21 X 21 X 3' i concrete I 32 I lin.ft.I $13.50 I $431
<br /> Prep Plant 192, X 225, i concrete I 20,700 I sq.ft. I $2.78 I 557,373
<br /> Dryers - 2 12(42' X 741) I concrete I 6,216 I sq.ft. I 52.78 I $17,229
<br /> Shop 1401 X 501 I concrete I 2,000 i sq.ft. I $2.78 I $5,543
<br /> Crusher 122' X 54, I concrete I 1,188 I sq.ft. I $2.78 I $3,293
<br /> Storage Bins - 5 140 - 21 X 2' X 31 I concrete I 80 I Lin.ft.I $13.50 I $1,077
<br /> Powder Magazines - 2 12(8' X 121) I concrete I 192 I sq.ft. I $2.78 I $532
<br /> Powder Magazine 113' X 24' I concrete I 312 ( sq.ft. I $2.78 I 5865
<br /> I i I I I I
<br /> I I I i I I
<br /> I I I I I I
<br /> I I I I I I
<br /> TASK SUBTOTAL - sheet 5 5598,428
<br />
|