C- 1981 -022 <br />PR -7 Findings <br />October 4, 2012 <br />The permit was transferred from Oxbow Carbon & Minerals, Inc. to Oxbow Mining, Inc. on <br />January 23, 1998 with Succession of Operator No. 4 (SO -04). <br />Oxbow Mining, Inc. submitted an application for permit renewal (RN -03) on March 13, 1998. <br />The submittal was called complete by the Division on March 23, 1998, thereby securing the right <br />of successive renewal for the Sanborn Creek Mine. The Division's adequacy review letter was <br />dated July 30, 1999. Because the operator chose to rewrite and reorganize the entire Sanborn <br />Creek Mine permit application, it was decided to separate the permit application reorganization <br />effort from the permit renewal process. Since the permit renewal adequacy questions were more <br />pertinent to the reorganization, rather than to the permit renewal itself, the OMI responses to the <br />permit renewal adequacy review questions were submitted in a new Permit Revision No. 4. RN- <br />03 was approved on September 25, 2000. <br />Permit Revision No. 4 (PR -04) was submitted September 5, 2000, and called complete <br />September 15, 2000. DMG issued the decision on January 9, 2002. Because of computer <br />problems with the Department of the Interior, the final AVS check was not accomplished until <br />January 16, 2002. During the review of PR -04, the Division conducted a complete bond <br />inspection of the mine and recalculated the reclamation bond liability at $3,117,145.00. <br />On September 19, 2001, Oxbow Mining, Inc., initiated the process of transferring the coal permit <br />from that entity to Oxbow Elk Creek, LLC, and then to Oxbow Mining, LLC ( OMLLC). This <br />transfer of permit (SO -05) received approval on October 22, 2001. No comments were received, <br />and the transfer became effective November 20, 2001. <br />OMLLC submitted an application for Permit Revision No. 5 (PR -05), received by the Division <br />on February 15, 2003, to revise the Elk Creek Mine longwall plan and add a 160 -acre lease <br />modification to accommodate a reorientation of the longwall panels. The area of the lease <br />modification was within the approved permit area. The application was initially found <br />incomplete because the package did not contain information on the possible effects of subsidence <br />on groundwater and surface water hydrology. Additional information was submitted and the <br />application was called complete on August 1, 2002. Upon the submission of a revised D -seam <br />subsidence report for the amended longwall orientation, PR -05 was approved on January 20, <br />2003. The federal mine plan approval was signed June 23, 2003 for mining in the D -seam. <br />OMLLC submitted an application for permit renewal (RN -04) on February 21, 2003. The <br />submittal was called complete by the Division on March 3, 2003, thereby securing the right of <br />successive renewal for the Sanborn Creek Mine. A preliminary adequacy letter was sent to <br />Oxbow Mining LLC on March 10, 2003. Oxbow submitted materials to satisfy stipulations 25 <br />and 34. A complete bond inspection was performed and the bond liability was confirmed as <br />$3,117,045.00. RN -04 was approved on October 3, 2003. <br />On January 11, 2008, the Division notified Oxbow Mining, LLC of the impending permit <br />renewal (RN -05) and the need to file a complete application by April 14, 2008. OMLLC <br />7 <br />