Laserfiche WebLink
-7- <br /> Fixed time - 1.1 minutes <br /> Haul time 0% resistance - 1 .45 min. <br /> Return time 6% resistance - 1.65 min. <br /> Cycle Time 4.2 min. <br /> A total of 3 scrapers can be loaded by one D9L. Therefore, 6. 5 hours would be <br /> required for this portion. <br /> A total of 1,300 CY of topsoil must be replaced on the bus garage ponds. The <br /> haul distance is 3,100 feet. A 637D scraper would have the following cycle <br /> time. <br /> Fixed time - 1.1 minutes <br /> Haul time 0% resistance - 1 .25 min. <br /> Return time 6% resistance - 1 .45 min. <br /> Cycle Time .8—min. <br /> A total of 3 scrapers can be loaded by one D9L. Therefore, 3.8 hours are <br /> required to complete this portion. <br /> The cost for topsoiling the portal area and sediment ponds is $9,998.00. <br /> Portal Sealing pJ C <br /> Mean' s Crew C-20 can pour 105 CY per day. The concrete plug required 56 cubic <br /> yards. Therefore, 4.25 hours are required to complete this job. At $2,061.00 <br /> per day, the total cost for installing the plug would be $1,100.00. <br /> Revegetati on C, 'i <br /> The reclamation plan requires seeding and mulching, plus fertilization if <br /> necessary. It is assumed that at least one application of nitrogen and <br /> phosphorus will be required. Also, it is assumed that the disturbed areas <br /> will be mulched at the rate of two tons per acre. The cost per acre is broken <br /> down as follows : <br /> Mulch 2 tons/acre @ $75.00/ton = $ 150.00 <br /> Mulch spreading @ 4 acres/day/person = 36.00 <br /> Fertilization = 40.00 <br /> Seed = 200.00 <br /> Hand Seeding = 30.00 <br /> Total Cost Per Acre $ 456.00 <br /> ;A total of 13.5 acres will be required to reclaimed. This figure is above <br /> that determined by Mid-Continent because a disturbance corridor of 75 feet was <br /> used rather than 50 feet. The total cost for revegetation would be $6, 156.00. <br />