T=11 <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />No concerns <br />Summary of Planning Items: <br />Continue clear and grub activities for the Mill Site Earthworks project <br />Continue subgrade preparation for fill placement for the Mill Site Earthworks project. <br />Continue slope contouring for the Mill Site Earthworks project. <br />Continue overburden fill placement for the Mill Site Earthworks project. <br />Continue confirmatory drilling of Underground Workings for the Mill Site Earthworks project. <br />Continue grouting "miss" (non -void) holes from confirmatory drilling. <br />Continue investigation and remediation of Underground Workings for the Mill Site Earthworks project. <br />Continue construction of the catch berm and storm water channel for the Mill Site Earthworks project. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC& V: <br />CCTV held a weekly construction meeting on May 1, 2012. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />None <br />AMEC: <br />None <br />Summary of Incidents /Accidents /Health & Safety Issues: <br />None <br />We trust the information provided clearly represents <br />May 5, 2012. <br />Joseph Hickey, CQA <br />Approved By: <br />findings and observations for the week ending <br />Date: May 5, 2012 <br />Date: Al (4* ,L,r <br />MEW Weekly Report WE 05.05.2012 <br />