ameO <br />D) Overburden Fill Placement <br />Overburden fill material was delivered from CC &V Mine Operations throughout both day and night <br />shifts. An Ames CAT D -10 dozer was used to maintain the borrow area. A CAT 993 front -end <br />loader and a CAT 992 front -end loader was used to load overburden fill material into CAT 40 -ton <br />articulating and CAT 777 haul trucks. <br />Loose, unconsolidated material from below Underground Working #4043 (Morning Glory) was <br />loaded into CAT 740 articulating haul trucks using a John Deere 850 excavator. The material was <br />hauled and placed as overburden fill. <br />Overburden fill was placed in the areas shown on Figure 1. A CAT 330 excavator and a CAT 312 <br />excavator with a hammer attachments "broke up" oversize boulders before they were placed in <br />the fill. Overburden fill was placed in 18" to 24" lifts using various CAT dozers, keying into existing <br />slopes when necessary. Each lift was moisture conditioned using a CAT 773 water truck (when <br />necessary) and compacted using a 10 -ton vibratory smooth drum compactor, passing over the <br />entire fill surface at least 4 times (method compaction technique was applicable). <br />Subgrade temperatures were monitored by an AMEC field representative prior to fill placement. <br />Fill material was not placed until the entire fill area was at or above 32 °F. Fill temperatures were <br />then monitored every hour during ambient temperatures below 32 °F. No frozen material was <br />placed during the week. <br />E) Slope Contouring <br />Slope contouring was performed using a CAT 345 excavator. Material generated during slope <br />contouring was placed as overburden fill at the top of the slope. <br />F) Soil Liner Fill (SLF) <br />No work performed during the week. <br />G) Drain Cover Fill (DCF) <br />No work performed during the week. <br />Location <br />This Week <br />Cumulative <br />Comments <br />DCF Process <br />- <br />158,613 <br />DCF processing is temporarily paused <br />Total <br />- <br />158,613 <br />DCF processing is temporarily paused <br />H) Underdrain <br />Construction of the Secondary Underdrain continued excavating approximately 780' of a 3'x4' <br />trench along the surveyed alignment using a CAT 345 excavator. Secondary underdrain <br />installation was performed installing 12 oz/yd2 geotextile and a 2' lift of Underdrain Filter Material <br />(UFM) was then placed in the trench, "burrito wrapping" the UFM material with the geotextile. A 6- <br />inch lift of select structural fill (SSF) was then placed over the geotextile using a CAT 950 front - <br />end loader. The SSF material was moisture conditioned and compacted using a vibratory plate <br />compactor. Approximately 330 linear feet of secondary underdrain was completely installed. <br />Overburden fill placement was then performed over the underdrain. Underdrain construction was <br />observed by an AMEC field representative and found to be constructed in accordance with design <br />drawings and project specifications. <br />MEW Weekly Report WE 03.10.2012 <br />