amee" <br />D) Remediation <br />Remediation of Underground Working #4016 continued as the fill progressed in the area. A CAT <br />345 excavator was used to place small lifts of overburden fill into the working and bucket tamp the <br />material. This was performed due the working being too narrow for the CAT 563 vibratory smooth <br />drum compactor to be used for compaction. Remediation will continue as the overburden fill <br />placement progresses in the area. <br />Underground Working #4049 was "cleaned out" using a Hitachi 350 excavator and observation <br />was performed by an AMEC field representative. The location was staked by the Ames surveyor. <br />Signs of a shaft or stope were encountered in the area during the excavation. Confirmatory drilling <br />will be performed for this working when a drill is available. <br />Investigation and remediation of Underground Working #4067 was performed using a CAT 330 <br />excavator to remove the timbers and rail that could possibly be an old narrow gauge rail bridge. <br />The timbers and any unsuitable materials were removed and hauled to a stockpile designated by <br />CC &V. <br />Underground Working #4068 was "cleaned out" using a CAT 330 excavator and observation was <br />performed by an AMEC field representative. The location was staked by the Ames surveyor. <br />Signs of a shaft or stope were encountered in the area during the excavation. Confirmatory drilling <br />will be performed for this working when a drill is available. The working was backfilled with native <br />material for safety. <br />E) Structures <br />No work performed during the week. <br />III) Geosynthetics <br />A) Geomembrane Installation <br />No work performed during the week. <br />B) Anchor Trench <br />No work performed during the week. <br />Q Geomembrane Exposure <br />No work performed during the week. <br />D) Geomembrane Acceptance <br />No work performed during the week. <br />IV)Storm Water Management <br />A) Best Management Practices (BMP) <br />Best Management Practices are being observed throughout the Mill Site Earthworks project. <br />MEW Weekly Report WE 03.03.2012 <br />