W 11 <br />LTM <br />tests were performed with results passing. Moisture - density relations were performed in <br />accordance with ASTM D698 -07. <br />A Hitachi 350 excavator was used to excavate the blasted material from Underground Working <br />#4029 and #4031. <br />Investigation and construction of an access road were performed at Underground Working #4044 <br />using a Hitachi 350 excavator. The existing concrete cap was removed from the working. Caution <br />tape was placed around the shaft for safety. <br />Investigation and remediation of Underground Working #4050 was performed using a CAT 330 <br />excavator to remove the timbers and rail that could possibly be an old narrow gauge rail bridge. <br />The timbers and any unsuitable materials were removed and hauled to a stockpile designated by <br />CC &V. The working was backfilled with structural fill in 18" to 24" lifts using various CAT dozers. <br />Each lift was moisture conditioned using a CAT 773 water truck (when necessary) and compacted <br />using a 10 -ton vibratory smooth drum compactor, passing over the entire fill surface at least 4 <br />times (method compaction technique was applicable). <br />Investigation and remediation of Underground Working #4067 was performed using a CAT 330 <br />excavator to remove the timbers and rail that could possibly be an old narrow gauge rail bridge. <br />The timbers and any unsuitable materials were removed and hauled to a stockpile designated by <br />CC &V. <br />D) Structures <br />Relocation of the structure at Underground Working #4043 (The Wedge) was finished by Frontier <br />Environmental Services Inc. <br />III) Geosynthetics <br />A) Geomembrane Installation <br />No work performed during the week. <br />B) Anchor Trench <br />No work performed during the week. <br />C) Geomembrane Exposure <br />No work performed during the week. <br />D) Geomembrane Acceptance <br />No work performed during the week. <br />IV)Storm Water Management <br />A) Best Management Practices (BMP) <br />Best Management Practices are being observed throughout the Mill Site Earthworks project. <br />MEW Weekly Report WE 02.25.2012 <br />