"Wilm <br />MILL SITE EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: Mill Site Earthworks <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Mill Site Earthworks <br />Date: February 25, 2012 <br />Reporting Period: 2/19/2012 through 2/25/2012 <br />Days <br />S <br />M <br />T <br />W <br />T <br />F <br />S <br />Work Shifts <br />- <br />D <br />D <br />D <br />DI <br />DI <br />D <br />- <br />N <br />N <br />N <br />N <br />I N <br />I N <br />D = Day Shift <br />N = <br />Night Shift <br />Project No.: 84201125K0 <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day /Night <br />Ambient Temperature Range (F): Low: 1'F to 28 °F ( + / -) High: 22 °F to 44 °F <br />AMEC CQA: Personnel On -site through the Reporting Period (See Attachment A). <br />Ames: Work activities were limited on Thursday (2/23/2012) due to snowfall and slick haul routes. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />I) Earthworks <br />A) Topsoil Stripping <br />Topsoil stripping and re- location was performed within the Mill Site footprint using various CAT <br />dozers pushing the material into stockpiles. The stockpiles were loaded into CAT 40 -ton <br />articulating haul trucks using a CAT 385 excavator, a John Deere 850 excavator, a CAT 992 <br />front -end loader, and a CAT 988 front -end loader. The topsoil was placed in a stockpile area <br />designated by CC &V. The stockpile area was maintained using various CAT dozers and a CAT <br />motor - grader. <br />B) Clear and Grub <br />Clear and grub activities were performed by Seedmasters for the Mill Site Earthworks project. A <br />John Deere 135 excavator, a Volvo 160 excavator, a John Deere 850 dozer, a CAT D -6 dozer, <br />and a skid steer loader were used to remove trees and shrubs from the area. These trees and <br />shrubs will be hauled to a chipping area designated by CC &V and are chipped and mixed into the <br />topsoil as it is placed. <br />C) Subgrade Preparation <br />Subgrade preparation was performed prior to structural fill placement in the areas shown on <br />Figure 1. Various CAT dozers were used to rip the existing surface to a depth of at least 6 inches. <br />Moisture conditioning of the subgrade was performed (when necessary) using a tandem axle <br />water truck. Compaction was performed using a 10 -ton vibratory smooth drum compactor passing <br />over the entire subgrade surface at least four times. The subgrade was inspected and approved <br />by an AMEC field representative, prior to fill placement. <br />MEW Weekly Report WE 02.25.2012 <br />