Laserfiche WebLink
GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />No concerns <br />Summary of Planning Items: <br />Continue clear and grub activities for the Mill Site Earthworks project. <br />Continue stripping topsoil for the Mill Site Earthworks project. <br />Continue subgrade preparation for fill placement for the Mill Site Earthworks project. <br />Continue slope contouring for the Mill Site Earthworks project. <br />Continue structural fill placement for the Mill Site Earthworks project. <br />Continue confirmatory drilling of Underground Workings for the Mill Site Earthworks project. <br />Continue grouting "miss" (non -void) holes from confirmatory drilling. <br />Continue investigation and remediation of Underground Workings for the Mill Site Earthworks project. <br />Continue structure removal /relocation for the Mill Site Earthworks project. <br />Continue DCF processing for the Mill Site Earthworks project. <br />Continue construction of the catch berm and storm water channel for the Mill Site Earthworks project. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC &V: <br />CC &V held a weekly construction meeting on January 24, 2012. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />None <br />AMEC: <br />Jay Moore (AMEC- Project Certifying Engineer) was onsite Wednesday, January 25, 2012 to observe <br />site activities, progress, and scheduling. <br />Summary of Incidents /Accidents /Health & Safety Issues: <br />None <br />We trust the information provided clearly represents our findings and observations for the week ending <br />January 28, 2012. <br />Joseph Hickey, CQA Monitor Date: January 28, 2012 <br />Approved By: Date: <br />MEW Weekly Report WE 01.28.2012 <br />