Laserfiche WebLink
subgrade is inspected for organics and debris by an AMEC field representative prior to fill <br />placement (keying into the subgrade). <br />D) Structural Fill Placement <br />A CAT 992 front -end loader and a CAT 993 front -end loader were used to load structural fill <br />material from a borrow area designated by CC &V. The material was loaded into 40 -ton <br />articulating haul trucks and hauled to fill areas. The fill excavation was assisted by various CAT <br />dozers. <br />Structural fill was placed in the areas shown on Figure 1. Structural fill was placed in 18" to 24" <br />lifts using various CAT dozers, keying into existing slopes when necessary. Each lift was moisture <br />conditioned using a tandem axle water truck (when necessary) and compacted using a 10 -ton <br />vibratory smooth drum compactor, passing over the entire fill surface at least 4 times (method <br />compaction technique was applicable). <br />Subgrade temperatures were monitored by an AMEC field representative prior to fill placement. <br />Fill material was not placed until the entire fill area was at or above 32 °F. Fill temperatures were <br />then monitored every hour during ambient temperatures below 32 °F. No frozen material was <br />placed during the week. <br />E) Slope Contouring <br />Slope contouring was performed in the fill areas that were close to finish grade. A CAT D -6 dozer <br />excavator was used to performed the slope contouring. Any excess material generated was <br />pulled up into the structural fill placement in the area. <br />F) Soil Liner Fill (SLF) <br />No work performed during the week. <br />G) Drain Cover Fill (DCF) <br />Processing of Drain Cover Fill (DCF) was performed at the DCF process area using a CAT D -9 <br />dozer during night shift. The processed material was hauled to a stockpile area, on Dump 4 <br />designated by CC &V using 40 -ton articulating haul trucks. The stockpile pile was maintained <br />various CAT dozers. <br />Location <br />This Week <br />Cumulative <br />Comments <br />(tons) <br />(tons) <br />DCF Process <br />35,275 <br />136,865 <br />Total <br />35,275 <br />136,865 <br />II) Underground Mine Workings <br />A) Discovery <br />During topsoil stripping, an Underground Working was encountered. The working was given a <br />number (UG #4041) by an AMEC representative and surveyed by Ames. Investigation of the <br />working will be performed at a later date. <br />MEW Weekly Report WE 01.28.2012 <br />