_ 4` <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed stripping, hauling, and stockpiling of topsoil from within the Mill Site Earthworks project. <br />AMEC observed subgrade preparation within the Mill Site Earthworks project prior to structural fill <br />placement. Subgrade temperatures were monitored prior to any fill placement. <br />AMEC observed excavation and placement of structural fill within the Mill Site Earthworks project. <br />Ambient, existing, and placed fill temperatures were monitored throughout the week. <br />AMEC observed cleaning out of UG #4001. <br />AMEC observed investigation and remediation of UG#4002. <br />AMEC observed investigation and remediation of UG #4003. <br />AMEC observed relocation of the Dump 4 SLF stockpile. <br />Testing Summary <br />Laboratory testing continued (Particle Size Distribution, Atterberg Limits, Moisture - Density Relations, <br />Specific Gravity, Permeability, and Point Load testing) for sampled materials. <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />No concerns <br />Summary of Planning Items: <br />Continue clear and grub activities for the Mill Site Earthworks project. <br />Continue stripping topsoil for the Mill Site Earthworks project. <br />Continue subgrade preparation for fill placement for the Mill Site Earthworks project. <br />Continue structural fill placement for the Mill Site Earthworks project. <br />Continue confirmatory drilling of Underground Workings for the Mill Site Earthworks project. <br />Continue investigation and remediation of Underground Workings for the Mill Site Earthworks project. <br />Continue structure removal for the Mill Site Earthworks project. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC &V: <br />The normal Weekly Construction meeting was rescheduled for Tuesday January 3, 2012. <br />MEW Weekly Report WE 12.24.2011 <br />