Laserfiche WebLink
ITE <br />M <br />DESCRIPTION <br />DATE <br />1 <br />Relocate 2 Park Lateral to pipeline <br />Fall 2011 <br />2 <br />Construct Surface Facilities <br />Extend and/or Relocate Utilities for Facility Area <br />Fall 2012- <br />Spring 2013 <br />3 <br />Complete mining at NH2, Construct Equipment Corridor, Move <br />Equipment to NHN and Reclaim Equipment Corridor <br />Mid 2013 <br />4 <br />Mine NHN Area <br />Mid 2013 - <br />Mid 2018 <br />5 <br />Relocate 2 Park Pipeline to Original Ditch Location <br />2016 <br />6 <br />Re- topsoil and re- vegetate final cut area <br />2019 <br />7 <br />Continue to irrigate and monitor reclaimed areas until final bond release. <br />2029 <br />TABLE 2.05.3 -3 - TIMING OF OPERATIONS <br />(Describe milestones related to NHN) <br />Section 2.05.3 Page 9 November 2011 <br />