Using the above mentioned unit costs, CBCI's total estimated reclamation costs are: <br />• Distribute Cap Materials: 11,200 yd @ $3.10 /yd = $34,720 <br />• Seed Mix: 3 seasons of 201bs /ac @ 4.5ac @$5.25/1b of seed = $1,418 <br />• Scarify and Broadcast Seed: 4.5 acres @ $2,500 /acre = $11,250 <br />• TOTAL RECLAMATION COSTS = $47,388 <br />The desired condition of the surface to be reclaimed will be to equal or exceed the July 2012 vegetative <br />conditions. As per the last DRMS site inspection (September 20, 2011), the vegetative conditions inside <br />the boundary of the 112 permit were considered successful, or nearly so. <br />Rule 3.1.5(7) requires that, upon reclamation, the sedimentation pond slopes cannot be any steeper than <br />1:2 (V:H), except from 5 feet above and 10 feet below the expected water line where slopes must be 1:3 <br />(V:H). Given the surface dimensions of the planned sedimentation pond these criteria can be met, and the <br />historic detention time of 12 hours at 1,000 gpm can still be achieved. In the event that the sedimentation <br />pond slopes do not meet reclamation criteria CBCI will grade and fill the pond using stored materials <br />from Stockpile 1 if needed. No additional costs are anticipated to do so, since the total volume of <br />materials to be moved does not change. <br />Prior to submitting this TR, CBCI currently has a financial warranty of $25,000 towards reclamation <br />under the 112 permit. Under separate cover, CBCI has submitted an additional $50,000 for financial <br />warranty to the Mined Land Reclamation Board to accommodate reclamation costs for the proposed <br />revisions in this TR. Therefore, the 112 permit currently has financial warranty of $75,000, which CBCI <br />believes is more than adequate to accommodate reclamation of the site. <br />Technical Revision, Camp Bird Mine 112 Permit (Permit No. M- 1982 -090) Page 11 <br />