Laserfiche WebLink
-6- <br /> 2. Conveyor corridor station 34+00 to 40+50 <br /> The average haul distance here is 400 feet. A 637D scraper has the following <br /> cycle time: <br /> Fixed time - 1 .1 minutes <br /> Haul time (6% total resistance) .45 min. <br /> Return Time (0% total resistance) 30 min. <br /> Cycle Time 1.97TTF7. <br /> With this cycle time, 637D scraper can move 702 CY per 50 minute work hour. A <br /> total of 2,700 CY must be moved. Only one scraper could be assisted by one <br /> D9L dozer with this short cycle time. Therefore, the following is the cost <br /> for this portion of the operation. <br /> 1 - D9L dozer @ $144.29/hr. = $ 548.00 <br /> 1 - D8L dozer @ $110.10/hr. = 418.00 <br /> 1 - 637D scraper @ $208.79/hr. = 793.00 <br /> 3 - Operators @ $54.00/hr. = 205.00 <br /> Total Cost $ 1,964.00 <br /> 3. Bin bench and fill area <br /> The average haul distance to the bin bench and fill area is 1 ,000 feet. A <br /> 637D scraper would have the following cycle time. <br /> Fixed time 1 . 1 minutes <br /> Haul time (6% total resistance) .80 min. <br /> Return Time (0% total resistance) .50 min. <br /> Cycle Time 2.4_m1n - <br /> With this cycle dime two scrapers can be loaded by one D9L. A 637D ca <br /> complete-18.5 cycles in a 50 minute work hour for a total of 481 CY/hr d <br /> total-of 14,500 CY of topsoil must be moved. With two scrapers, the Sob o <br /> be completed in 30 hours at the following cost: Z <br /> 1 - D9L dozer @ $144.29/hr. = G� �'.�� $ 4,329.00 <br /> 1 - D8L doter @ 110. 10/hr. _ ;t� 2, 527.00 % <br /> \\ 2 - 637D s 12 <br /> scrapers @ 417.58/hr. _ �t���" , .40 <br /> 00 _ <br /> 4 - Operators @ 72.00/hr. 2,16060 <br /> Total-Cost- --" l $ 22,319.00 <br /> 4. Portal Area and Sediment Ponds <br /> A total of 2,000 CY of topsoil will be required to be replaced on the portal <br /> area and pond. The haul distance to the portal area is 3,600 feet. A 637D <br /> scraper will be used to haul the topsoil . The scraper cycle time is as <br /> fol Io':rs: <br />