WESTERN STATES RECLAMATION, INC. <br /> September <br /> ID ACTIVITY Duration Scheduled Start 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 <br /> 1 Mobilization 1 d 9/7197 8:OOam <br /> 2 Seed Collection 5d 9/9/97 B:OOam <br /> 3 Imprinting 12d 9/8/97 B:OOam <br /> 4 Soil Prep 12.8d 9/10/97 8:OOam <br /> 5 Hydroseed 13d 9/12/97 8:OOam <br /> 6 BFM 12d 9/15/97 B:OOam <br /> 7 Straw Mulch 8d 9/15/97 8:OOam <br /> 8 Demob 1 d 9/30/97 8:OOam <br /> Imprinting, soil prep, and hydroseeding will occur on intermittent days to comply with the need to <br /> install straw mulch or BFM no later than 48 hours after seeding. <br /> Project: COAL BASIN Critical Progress Rolled Up <br /> Date: 9/4/97 Noncritical ®_ Milestone <br />