Laserfiche WebLink
1 <br /> Construction Summary <br /> Staked channel centerline and cross-section locations and excavated approximately 27,000 <br /> cubic yards of material. 80% of material used to build southeast channel sides; 15% stockpiled <br /> near northernmost portion of channel for future use, 5% used at southwest area. Placed 3,500 <br /> cubic yards of riprap in channel. Plugged old channel. <br /> V. FUTURE MAINTENANCE <br /> Possibly need to place additional riprap in coal creek across from Dutch Creek confluence. <br /> Project Manager: Steve Renner <br /> Date: December 3, 1998 <br />