Date: September 07, 1995 Attn: Jim McArdel
<br /> Contractor: Gary Rinderle Construction, Inc. Project Name,Coal Basin/Mine 3 Reclamation Project
<br /> Address: 542 33 Road Project#: PKA-5-359
<br /> Clifton, Colorado Location: Pitkin County, Redstone, CO
<br /> 81520 Owner: State of Colorado, MLRD
<br /> BID SCHEDULE PAY REQUEST# 2
<br /> PERCENTAGE COMPLETE INVOICE # 2
<br /> BID BID PERCENT
<br /> ITEM# DESCRIPTION AMOUNT COMPLETE SUB TOTAL TOTAL
<br /> 1 Mobilization/Demobilization
<br /> per specifications 10,000.00 66.60% $6,660.00 $6,660.00
<br /> 2 Demolition, per specifications 10,000.00 100.00% $10,000.00 $10,000.00
<br /> 3 Silt fence, per specifications 4,200.00 90.00% $3,780.00 $3,780,00
<br /> 4 Earth work, per specifications
<br /> a Mine 3 81,000.00 100.00% $81,000.00 $81,000.00
<br /> b Intermediate Transfer Area 7,800.00 100.00% $7,800.00 $7,800.00
<br /> c Lower Bench Area 14,700.00 100.00% $14,700.00 $14,700.00
<br /> 5 Surface Drainages (Furrows),
<br /> per specifications
<br /> a Mine 3 2,250.00 100.00% $2,250.00 $2,250.00
<br /> b Intermediate Transfer Area 200.00 100.00% $200.00 $200.00
<br /> c Lower Bench Area 600.00 100.00% $600.00 $600.00
<br /> 6 Equipment Rental,
<br /> per specifications(if required)
<br /> a Bulldozer 3,200.00 $0.00 $0.00
<br /> b Backhoe Loader 800.00 $0.00 $0.00
<br /> 7 Revegetation, per
<br /> specifications
<br /> a Steeper than 31-1:1 V 35,000.00 $0.00 $0.00
<br /> b Flatter than 3H:1V 15,000.00 $0.00 $0.00
<br /> 8 Additional Surface Drainages,
<br /> per specifications (if required) 1,050.00 $0.00 $0.00
<br /> 9 Additional Silt fence,
<br /> per specifications (if required) 2,400.00 $0.00 $0.00
<br /> ---------------------------------------------------
<br /> TOTAL CONTRACT $188,200.00 SUBTOTAL $126,990.00 $61,210.00 Contr. Bal.
<br /> TOTAL BILLED TO DATE $126,990.00 TOTAL
<br /> Less Previous Billing ($44,787.60)
<br /> Total Due This Request $82 202.40
<br />
|