EXHIBIT L - RECLAMATION COST ESTIMATE
<br /> *************'***CURRENT BOND *"*«********* ***"**" *************'**PROPOSED BOND
<br /> Unit Cost Unit Quantity Extended Cost Unit Cost Unit Quantity Extended Cost
<br /> s s s s
<br /> -Fine Grade Pond $150 acre 30 $4,500 $150 acre 16 $2,400
<br /> -Tailings Amendment $1,000 acre 22 $22,000 $1,000 acre 16 $16,000
<br /> -Seed, Mulch, Fertilize $1,000 acre 30 $30,000 $1,000 acre 16 $16,000
<br /> -Borrow Area-Seed, Mulch, Fertilize $800 acre 5 $4,000
<br /> -Riprap Side Outfall of Pond $10 C.Y. 800 $8,000
<br /> -Monitoring&Maintenance $4,025 L.S. 1 $4,025 $20,500 L.S. 1 $20,500
<br /> Engineering Building,Shop&Settling Pond Area
<br /> -Surface Facilities Dismantaling&Disposal or Removal $15,000 L.S. 1 $15,000
<br /> -Rough Site Grading $300 acre 8 $2,400
<br /> -Fine Grading&Seed Bed Prep. $150 acre 8 $1,200
<br /> -Seed, Mulch, Fertilize $800 acre 8 $6,400
<br /> -Monitoring&Maintenance $1,250 L.S. 1 $1,250 $1,250 L.S. 1 $1,250
<br /> Decant Ponds/PeatArea
<br /> -Rough Site Grading $300 acre 9 $2,700
<br /> -Fine Grading&Seed Bed Prep. $150 acre 9 $1,350
<br /> -Seed, Mulch, Fertilize $800 acre 9 $7,200
<br /> -Monitoring&Maintenance $563 L.S. 1 $563
<br /> Subtotal Mayflower Mill/Tailings Ponds $477,136 $239,198
<br /> Contingency,Administration,Contractor Profit Per Diem $243,715 $163,007
<br /> TERRY TUNNEL&AMERICAN TUN�BULKHEAD REPLACEMENT
<br /> -Bulkkhead Replacement $697,000 L.S. 1 $697,000 $697,000 L.S. 1 $697,000
<br /> TOTAL BOND $2,197,000 $1,250,060
<br /> Notes: 1)Mobilization and demobilization costs are included in the cost estimate
<br /> 2)Monitoring and maintenance costs were left intact for areas in the permit area
<br /> L-4