20 cannot be approved to allow the existing material to be left in place, GCC Energy <br />will move the coal mine waste within 45 days after being notified the Division's <br />decision. <br />October 1 thru October 15, 2012: If TR -20 determines that reworking the existing <br />material to some degree is the preferred solution, the approved TR -20 designs are <br />submitted to interested contractors for construction bids. Bids are reviewed by GCC <br />Energy, and construction contract awarded to successful bidder. <br />October 16 thru November 30, 2012: Construction activities required by TR -20 are <br />completed. The timing of this phase may depend, in part, on the results of the <br />geotechnical study and final scope of work determined by CDRMS approval. A final <br />construction and completion timeline will be included as a stipulation to TR -20. <br />