Description <br />Time Needed (months) <br />Initial Site Development <br />6.0 <br />Mine Processing Area <br />34.8 <br />Mine Phase 1. <br />16.8 <br />Reclaim Phase 1, and mine Phase 2. <br />7.9 <br />Reclaim Phase 2, and mine Phase 3. <br />12.0 <br />Reclaim Phase 3, and mine Phase 4 <br />12.3 <br />Reclaim Phase 4, and mine Phase 5 <br />12.6 <br />Reclaim Phase 5, and mine Phase 6 <br />8.8 <br />Reclaim Phase 6, and mine Phase 7 <br />13.8 <br />Reclaim Phase 7, and mine Phase 8 <br />14.1 <br />Reclaim Phase 8, and mine Phase 9. <br />13.6 <br />Reclaim Phase 9, and mine Phase 10. <br />8.9 <br />Reclaim Phase 10, and mine Phase 11. <br />13.5 <br />Reclaim Phase 11, and mine Phase 12. <br />12.4 <br />Reclaim Phase 12, and mine Phase 13. <br />12.4 <br />Reclaim Phase 13, and mine Phase 14. <br />8.0 <br />Reclaim Phase 14, and mine Phase 15. <br />6.3 <br />Reclaim Phase 15. <br />1.0 <br />Reclaim Processing Area <br />3.0 <br />Remove facilities, pull pit pump, and <br />reclaim other disturbed areas. <br />3.0 <br />Total (Months) <br />220.9 <br />Total (Years) <br />18.4 <br />2. Reclamation Timetable <br />The overall project timetable, including mining and reclamation is shown below. This table is based on <br />forecasted production rates (300,000 tons per year) and may change due to market conditions. Exhibit <br />L: Reclamation Costs describes the worst case bond scenario. <br />Table E -3 Reclamation Timetable <br />Reclamation will occur concurrently with each phase, such that no more than 10 acres of unreclaimed <br />area will be active at any one time, in addition to the 14.50 acres of processing area. <br />Steamboat Sand and Gravel Pit, April 2012 E -3 <br />