Hydrology <br /> Construction of intercept channels at the top and bottom of the <br /> waste bank and the relocation . of the natural eastside drainage <br /> channel are required. The top intercept channel will run the length <br /> of the waste bank at the top of the slope and be of sufficient size <br /> to carry the 100yr-24hr event. The contributing drainage area, <br /> above the bank, is approximately 8.3 acres. The Army Corps of <br /> Engineers ' HEC-1 Flood Hydrograph Package (HEC, 1981) was used to <br /> determine the design discharge. Total storm depth was obtained from <br /> the National Oceanic and Atmospheric Administration (NOAA) rainfall <br /> atlas (Miller, 1973) . Standard Soil Conservation Service methods, <br /> available within the HEC-1 package, were used to determine excess <br /> rainfall and unit hydrograph routing. The following table lists the <br /> watershed parameters used in determining the design discharge for <br /> the intercept channel. <br /> Watershed Parameters for Intercept Channel above Waste Pile <br /> Drainage Area = 8 . 3 acres <br /> Length to Divide z 500 ft <br /> Curve Number = 78 <br /> Average Slope = 48% <br /> Lag Time = 4 minutes <br /> The reach from section 1 to section 10 will be divided into two <br /> separate parts at section 6 and thus the contributing area to <br /> either channel will be half that listed in the table. The resulting <br /> peak discharge for each part is 4 cfs. <br /> A backwater analysis was performed to size the intercept channel <br /> using the U.S. Army Corps of Engineers ' HEC-2 , Water Surface <br /> Profiles computer model (HEC, 1982) . The channel will be triangular <br /> in shape with a 3 ft. top width, 1: 1 side slopes and will be placed <br /> on a minimum invert slope of 0. 010. The channel will be graded to <br /> drain from section 1 to section 4 and from section 6 to section 4 . <br /> Similarly the upper portion of intercept channel will drain from <br /> section 6 to section 7 and from section 10 to section 7 . Runoff <br /> collecting at sections 4 and 7 will be drained through an 18" <br /> diameter pipe down the waste bank and will terminate at the <br /> eastside drainage channel. A profile of the waste bank and the <br /> channels is shown in figure 3 . At the point where the flow exits <br /> the pipes the drainage channel must be armored with rip-rap (6" to <br /> 24" well graded) material to prevent local scour of the eastside <br /> drainage. Computer printouts for both the HEC-1 and HEC-2 runs <br /> discussed above are included in the appendix. <br /> A similar channel is required at the toe of the slope to <br /> 11 <br />