SPILLWAY RIPRAP DESIGN T • 40' <br />100- YR /24HR PEAK DESIGN FLOW - 6.58 CFS <br />Height of flow (Broad Crested Weir) - H =(Q /CL)"2 /3 <br />For C = 2.84, Q = 6.58 cfs, L = 84 in <br />H = 5.75 in, Spillway Elevation 0 5941.75, Crest 0 5943.0 <br />RIPRAP DESIGN - FROM PAP -0790 - SIMPUFIED DESIGN GUIDELINES <br />FOR RIPRAP SUBJECTED TO OVERTOPPING FLOW (BuRec, CSU) <br />D50 Cu"1 /4= 0.55(gf"0.52 /S "3 /4)(sin a /(Gs cos a -1) <br />(cos a tan phi -sin a)) "1.11 <br />D50= (0.55(gr0.52/S"3/4)(sin a /(Gc cos a -1) <br />(cos a tan phi -sin a)) "1.11)/Cu"1/4 <br />FOR NORTH POND - <br />D50 = median stone size (m) <br />Cu = coefficient of uniformity = 1.95, <br />of = unit discharge (m3 /m /s) = 0.087 <br />S = embankment slope (unitless) = 0.333, <br />a = embankment slope (degrees) = 18.43 <br />Gs = speciflc gravity of riprap = 2.24, <br />phi = angle of repose of the riprap = 42 <br />050 = 0.145M use 6.Oin <br />For interstitial flow, Vi (flow velocity) _ (gD50) "0.5 *2.48x"0.58 *CU" -2.22 <br />where s = slope in ft per ft = 0.333 <br />1/1 = ( 32. 16x( 6/ 12) ) "0.5x(2.48x(0.333)"0.58)x(1.95 ' -2.22) = 1.194 fps <br />Average velocity is the interstitial velocity multiplied by the porosity <br />(Np) of the riprap - Vav - Vi x Np. <br />for Np = 0.45, Vav = 1.194x0.45 = 0.537 fps. <br />Depth of flow is the flow quantity divided by the average velocity - <br />Y = Q/Vav, Y = (6.58/7ft.)/0.537fps = 1.75 ft. or 21.0 in., using <br />an integer multiple of 050 for thickness gives 4xD50 for 24 inches <br />of 6 in. D50 riprap. <br />.- <br />ONIT <br />\ <br />BASIN AREA <br />PA -N1 0.41 <br />PA -N2 0.56 <br />BASIN AREA <br />PA -N1 0.41 <br />PA -N2 0.56 <br />\ \ ^` <br />J <br />/ <br />f <br />To provide a safety factor use a riprap with a D50 of 9.0 in. <br />VI = ( 32.16x(9/12)) "0.5x(2.48x(0.333) "0.58)x(1.95" -2.22) = 1.46 fps <br />Vav = 1.46x0.45 = 0.66 fps. <br />Y = (6.58cfs/7ft) /0.66fps = 1.43 ft or 17.15 in, using an integer <br />multiple of D50 for thickness gives 2xD50 for 18 inches of 9 in D50 riprap. <br />DETENTION POND 10 YR /24-HR DESIGN VOLUME - <br />CN D10 VOLUME <br />88 0.941 1,402 <br />89 1.003 2,039 TOTAL - 3,441 <br />VOLUME PROVIDED 0 ELEVATION 5908.75 - 3926.5 <br />DETENTION POND 100 YR /24-HR DESIGN VOLUME - <br />CN 010 VOLUME <br />88 1.792 2,666 <br />89 1.873 3,807 TOTAL - 6,473 <br />ST DIVERSION SWALE SUB -BASIN PA N11 - FLOW <br />3 CFS <br />Channel Data: <br />Flowrate 1.13 cfs <br />Manning's n 0.0280 <br />Slope 0.0663 ft/ft <br />Height 24.0 in <br />Left slope 0.33 ft /ft (V/H) <br />Right slope 0.33 ft/ft (V/H) <br />Depth 3.76 in <br />Velocity 3.83 fps <br />Percent full 15.67 X <br />DUMP <br />SLOPE VARIES EXISTING <br />- <br />r GROUND <br />SECTION H-H -77 .. I. <br />T -20' <br />3 -INCH <br />LAYER OF <br />1 -1/2 -Inch <br />050 RIPRAP <br />T -8' <br />DUMP <br />T -20' <br />ALTERNATE RIPRAP FILTER - <br />in 6 -inch LAYER OF GRAVEL WITH A <br />c. MAX DIA OF 2 -inch, A 050 OF <br />N0.4, AND A MIN. OF NO. 100. <br />. <br />2.2 <br />GEOTEXT1LE - MIRAFI 1120N <br />OR EQUIVALENT <br />DETAIL THRU SPILLWAY <br />DATE: <br />DRAWN <br />--6.0' <br />3 <br />EXISTING -J <br />5905.00 <br />10 YR WSEL - <br />5908.75 <br />ELEVATION <br />5909.0 <br />5908.75 <br />5908.0 <br />5907.0 <br />2/11/11 <br />BY: JCP. JR <br />SHEET 4 OF 5 <br />AREA <br />4221.22 <br />3697.25 <br />2371.78 <br />1053.97 <br />CREST - <br />5910.00 ., <br />SECTION I-1 <br />T - 20' NORTH DETENTION <br />DETENTION POND 10 YR /24-HR DESIGN VOLUME - <br />VOLUME (CONIC) <br />4915.6 <br />3926.5 <br />1668.9 <br />0.0 <br />RIMROCK EXPLORATION & DEVELOPMENT <br />PRINCE ALBERT NINE - 1100 PERMIT APPLICATION <br />EXHIBIT U-4 - STRUCTURES 8 <br />Surface Water Control and Containment Facilities <br />JAMES C. PIERCE, JR. <br />P.O. BOX 100 <br />WUCLA, COLORADO 81424 <br />(070) 864 -7456 <br />