Bulldozer Worksheet Cont'd Task#293 Page 2 of 2 <br /> Job Condition Correction Factor Source <br /> Operator Skill: 0.750 (AVG.) <br /> Material consistency: 0.900 (CAT FIB)) <br /> Dozing method: 1.000 (GEN.) <br /> Visibility: 1.000 (AVG.) <br /> Job efficiency: 0.830 (1 SHIFT/DAY) <br /> Spoil pile: 0.800 (FND-RF) <br /> Push gradient: 0.903 (CAT HB) <br /> Altitude: 1.000 (CAT HB) <br /> Material Weight: 0.793 (CAT HB) <br /> Blade type: 1.000 (PAT) <br /> Net correction: 0.3209 <br /> Adjusted unit production: 224.63 LCY/hr <br /> Adjusted fleet production: 224.63 LCY/hr <br /> JOB TIME AND COST <br /> Fleet size: 1 Dozer(s) <br /> Unit cost: $0.884/LCY <br /> Total job time: 1.24 Hours <br /> Total job cost: $247.16 <br /> CIRCES Cost Estimating Software <br />