5. Hydrostatic Testing <br />The entire HDPE pipeline was hydro-statically tested as a complete assembly. <br />The contractor filled the Tine with water and pressurized the line to 240 psi at the <br />pump station end for four hours and then held for a one -hour hold period with no <br />significant pressure Toss. No leaks were found. <br />Conclusion <br />The 5 Dam Seepwater Pipeline replacement project has been completed and is in <br />general conformance with the project plans and specifications. The new seepwater <br />pipeline section is in operation and performing well. <br />R: \1000 \1051 \1051.19\1051.19.05 (Mayttower»Jocuments\close out report\close out reportrl .doc <br />