Laserfiche WebLink
TR 25 was received on 14 May 2010, deemed complete on 24 May 2010 and approved on 7 June <br />2010. TR-25 updated the permit boundary based on the decrease approved with Partial Phase <br />I/II/III Bond Release SL-06. <br />Partial Phase UIUIII Bond Release SL-06 was received on 10 October 2006, found incomplete on <br />8 December 2006, deemed complete on 7 January 2007 and approved on 22 December 2009. <br />SL-06 approved a full Phase III release on all areas that did not overly the workings, reducing the <br />current permit boundary to 1,086.00 acres. This release also included all of the remaining <br />surface areas with the exception of the 4.10 acres that comprise the passive treatment system for <br />the Portal #1 and Portal #3 mine water discharge. <br />III - STIPULATIONS <br />There are no stipulations on the permit. <br />IV - MIDTERM REVIEW AND ADEQUACY QUESTIONS <br />(Pursuant to Rule 2.08.3) <br />There are no adequacy questions for the remaining 4.10 acres of disturbance at the North <br />Thompson Creek Mine. <br />V - PERMIT VARIANCES AND SPECIFIC APPROVALS <br />There are no specific variances and approvals by the Division for the North Thompson Creek <br />Mines. <br />VI - BONDING SUMMARY <br />The Division holds an approved bond on behalf of the permitted North Thompson Creek Mines. <br />Bonding is in the form of a Certificate of Deposit in the amount of $100,000.00 (US Bank, NA <br /> . All of the required reclamation has been completed at the North Thompson <br />Creek Mine. The remaining facilities, which comprise the developed water resource, have been <br />permitted as permanent. <br />Pursuant to Rule 3.03.1(4), the Division has set the liability requirement for the North Thompson <br />Creek Mine at $10,000.00. This amount is the minimum required bond amount required until <br />bond for the entire permit area is fully released. The Division has set the $10,000.00 bond <br />amount because there is no remaining reclamation at the mine. <br />This concludes the Division's 2011 Midterm Review MT-06 for the North Thompson Creek <br />Mine. <br />North Thompson Creek Mines <br />2011 Midterm Review (MT-06) <br /> <br />C-1981-025 <br />-4- 15 June 2011