Third Adequacy Letter, Amended CN-01 I 6 <br />May Day Idaho Mine Complex <br />• Please avoid the splitting of small areas onto multiple maps. Please combine <br />Figures F-4 and F-4A onto one map. Please show the entire 8.2 acres of <br />reclaimed lands for the Pay Day and Idaho claims on one map. <br />• Figure F-4A indicates an 11 foot highwall at 1H:1V slope, which is in conflict with <br />the 2H:1V slope described in the reclamation plan. <br />• Figure F-5 shows a shed and an outhouse, not discussed in the reclamation plan. <br />• Figure F-5a redirects the Division to a different map for details of the final <br />configuration of the reclaimed area. Figure F-5a covers an area of 0.3 acres and <br />the 11 inch by 17 inch paper for Figure F-5a provides sufficient space to show the <br />final configuration of the reclaimed area. Please show the final configuration of <br />the entire Chief Portal area on the reclamation map, as required under Rule <br />6.4.6(a). <br />Figure F-5a indicates a 40+ foot highwall at 0.4H:1V, which is in conflict with the <br />1.5H:1V slope described in the reclamation plan. <br />11. The amended application includes approximately 32 maps, yet many of the existing and <br />proposed mine features are not shown correctly. Figure D-1 attempts to provide some <br />details for the mine plan at the May Day 1 level but incorrectly labels the mill facility as <br />"Storage", incorrectly locates the two water tanks, and shows contour lines on top of <br />the structures. Please revise Figure D-1 to correct these inadequacies. Please provide <br />similar scale maps to support the mine plan for each of the areas of affected lands. <br />Please correctly locate the major mine features, including but not limited to all <br />underground mine openings, mine benches, material stockpile areas, the proposed mill <br />facility, and any structures utilized to support the mining and milling operation. Please <br />submit detailed and correct maps, which are compliant with the basic map <br />requirements of Rule 6.2.1(2), and clearly delineate and label the existing and proposed <br />mine features. <br />12. The Division had previously requested a surface map which identifies the glory hole, <br />associated with the May Day 1 workings, and other pre-permit mine features associated <br />with the historic May Day and Idaho mines. The Applicant's response affirmed the glory <br />hole, and other pre-permit mine features, were located on several of the submitted <br />maps. The glory hole is not identified on any map. Please submit a surface map which <br />delineates and labels the glory hole, associated with the May Day 1 workings, and other <br />pre-permit mine features associated with the historic May Day and Idaho mines. Such <br />information is essential in identifying all locations whereby precipitation may enter the <br />underground locations proposed for disposal of mill tailings, waste rock, and debris from <br />the dismantled mill facility. <br />13. The Division had previously requested maps of the underground workings, labeling all <br />locations proposed for underground disposal of waste rock and mill tailings. The <br />Applicant's response directed the Division to Figure D-1a for such map. The submitted <br />information did not include a Figure D-1a, but there was a Figure D-113. Figure D-113 <br />attempts to show the underground locations for tailings disposal but the map is not <br />legible. Please submit a legible Figure D-113.