EXHIBIT L - Reclamation Costs <br />Reclamation Costs: <br />Overburden and excavated soil materials unsuitable for road construction have been used to backfill excavated <br />areas and for re-grading to stable slopes. Available stockpiled topsoil will be placed on re-graded areas prior to re- <br />seeding with approved plant type seed mixes. Final site reclamation costs do not include the cost of conversion of <br />the site to water storage. The slurry wall will cost approximately $2.8 million. The cost of the to-be-constructed <br />water storage facilities (outlet works, pumps, meters, and piping, fencing) is unknown. <br />It is anticipated that native dry land grass seed and mulch application will be required on the remaining non-pond <br />areas. <br />It is anticipated that final grading and placement of topsoils followed by re-seeding will cost less than $30,000. <br />M:\DAVE B\Geisert Pit\DRMS Permit Amendment\Geisert Amendment Application & Exhibits Revised 4-21-11.docx