<br /> CLIMAX MINE RECLAMATION COST ESTIMATE
<br /> Financial Reporting Unit Rates
<br /> East Side Channel Construction
<br /> Across Tenmile and Mayflower TSFs
<br />Assumptions:
<br />(1) Construction of the East Side Channel will be done in a manner similar to the completed portions that were done on Robinson TSF in 2005.
<br />(2) Knowing the costs for Robinson's East Side Channel, it can be assumed these numbers are applicable to Tenmile and Mayflower.
<br />(3) Preliminary sizing provided by Wheeler Feb-2010; spillways for Tenmile and Mayflower will be equivalent to Robinson's 2005 ESC.
<br />Tasks:
<br />(1) Construct Channel Extensions through Camp, Robinson, Tenmile, and Mayflower.
<br />(2) Construct Pipeline Extensions through Camp, Robinson, Tenmile, and Mayflower.
<br />Timing
<br />End of Mine Life
<br />Total Cost
<br />$11,967,396
<br />Calculations
<br />
<br />Task/Area
<br />Qty Units t:; Unit cost/unit
<br />Total Equip Cost
<br />Total Labor Cost Gost/Unit Total Material Cost Total Cost
<br /> Equip Labor Materials
<br />East Side Channel
<br />Construct Channel Extensions 29,300 ft $63.45 $1,394,218 $464,739 $1,858,958
<br />Geotextiles (furnish & install) 153,889 sq yd $2.08 $159,989 $159,989 $319,979
<br />Rip Rap Armoring along Channel Route 82,737 cy $30.75 $2,544,082 $2,544,082
<br />East Side Pipeline
<br />HDPE 42-48" pipe and bedding (furnish & install) 40,900 ft $177.12 $1,811,094 $1,811,094 $3,622,189 $7,244,378
<br /> - Total Equip Cost Total Labor Cost Total Material Cost Total Cost
<br />TOTAL COSTS $3,205,313 $2,435,823 $6,326,261 $11,967,396
<br />Climax Mine Permit Amendment AM-06 By Wheeler. 2/24/10
<br />Reclamation Construction Quantities
<br />East Side Channel Camp
<br />t
<br />i
<br />E Robinson
<br />E
<br />t
<br />i Tenmile Extension Mayflower
<br />EMension Total Units
<br />x
<br />ens
<br />on
<br />x
<br />ens
<br />on
<br /> Channel Length: 4,500 5,200 11,000 8,600 29,300 ft
<br /> Bottom Width: 6.0 6.0 10.0 16.0 ft
<br /> Channel Depth: 6.0 6.0 6.0 6.0 it
<br /> Side Slope: 2.0 2.0 2.0 2.0 (H):I(V)
<br /> Cross-Section Area: 108.00 108.00 132.00 168.00 sq It
<br /> Wetted Perimeter: 32.83 32.83 36.83 42.83 ft
<br /> Top Width: 30.00 30.00 34.00 40.00 ft
<br /> Channel Volume: 18,000 20,800 53,778 53,511 146,089 cu yds
<br /> Channel Excavation:
<br />Riprap Si- 18,000 20.800
<br />6.0 6.0 53,778
<br />12.0 53,511
<br />18.0 146,089 cu yds
<br />in
<br /> Riprap Thickness: 1.00 1.00 2.00 3.00 ft
<br /> Riprap Volume: 5,472 6,323 30,012 40,929 82,737 cu yds
<br /> Geotextile Length: 42.83 42.83 46.83 52.83 ft
<br /> Geotextile Area: 21,416 24,748 57,240 50,485 153,889 sq yds
<br /> Road Width: 20.0 20.0 20.0 20.0 ft
<br /> Road Surface Area: 90,000 104,000 220,000 172,000 586,000 sq ft
<br /> Surfacing Depth: 9.0 9.0 9.0 9.0 in
<br /> Surfacing Volume: 2,500 2,889 6,111 4,778 16,278 cu yds
<br /> Camp Extenstion = Camp (near TDH) to Hwy 91 crossing
<br /> Robinson Extension = Hwy 91 crossing to Robins on spillway structure
<br /> Tenmile Extensi on = outall 63" HDPE at 2 Dam to Clinton Gulch
<br /> Mayflower Extention = Clinton Gulch to Mayflower Creek
<br />East Side Pipeline
<br /> Pipe Length: 4,900 8,100 7,900 20,000 40,900 It
<br /> Pipe Size: 42 42 42 48 in
<br /> Material: ID PE SDR 1HOPE SDR 17 HDPE SDR 17 HD PE SDR 17 PE4710
<br /> Pipe W6ght: 135.372 135.372 135.372 176.812 Ibs/ft
<br /> Pipe Weight: 663,323 1,096,513 1,069,439 3,536,210 6,365,515 lbs
<br /> Pipe OD Arcs: 9.62 9.62 9.62 12.57 sq ft
<br /> Trench Side Space: 1.50 1.50 1.50 1.50 ft
<br /> Bedding Base: 0.50 0.50 0.50 0.50 ft
<br /> Bedding Cover: 0.50 0.50 0.50 0.50 ft
<br /> Soil Cover: 2.00 2.00 2.00 2.00 ft
<br /> Trench Width: 6.50 6.50 6.50 7.00 ft
<br /> Trench Depth: 6.50 6.50 6.50 7.00 ft
<br /> Trench Area: 42.25 42.25 42.25 49.00 sq ft
<br /> Trench Volume: 7,668 12,675 12,362 36,296 69,001 cu yds
<br /> Bedding Area: 19.63 19.63 19.63 22.43 sq ft
<br /> Bedding Volume: 3,562 5,889 5,743 16,618 31,812 cu yds