Laserfiche WebLink
Snowcap Coal Company Inc -9- 2010 Annual Reclamation Report <br />26. Conveyor Corridor - The conveyor corridor, from the Xcel culvert north to <br />Haul Road #3 was graded to approximate original contours and reseed. <br />A total of 0.5 acres in this area achieved final Phase III Bond Release with <br />SL -5, approved on November 5, 2009. Located in SE'/, Section 27 and <br />NW'/, Section 34, Township 10 South, Range 98 West, 6 th P.M. <br />Area - 2.7 acres <br />Date - July 2003 <br />Seed Mix - "Seed Mix, Table 14 -8 ", Lowland Components <br />Phase III Bond Release - 0.5 acres <br />27. Conveyor Corridor - The conveyor corridor, from the Xcel culvert south <br />to Transfer Building #2 and east of Colorado River where conveyor tube <br />crossed river was graded to approximate original contours and seeded. A <br />total of 1.3 acres in this area achieved final Phase III Bond Release with <br />SL -5, approved on November 5, 2009. Located in SE'/, Section 27 and <br />NW'/, Section 34, Township 10 South, Range 98 West, 6 th P.M. <br />Area - 1.6 acres <br />Date - March 2004 <br />Seed Mix - "Seed Mix, Table 14 -8 ", Lowland Components <br />Phase III Bond Release - 1.3 acres <br />28. Substations A - Superstructures, fences, slabs and components <br />removed during 2007. Graded to approximate original contours and re- <br />seeded. Located in the SE'/ Section 34, Township 10 South, Range 98 <br />West, 6 th P.M. <br />Area - 0.2 acres <br />Date - August 2007 <br />Seed Mix - "Seed Mix, Table 14 -8 ", Upland Components <br />29. Roadside South Portal Mine Facilities and Stockpile /Prep Plant Area <br />and Conveyor Tunnel Under 1 -70 - The Roadside South Portal Mine <br />Facilities, Stockpile and Prep Plant areas where reclaimed as per <br />approved Permit Revision #3 (PR -3). 13.5 acres were reclaimed during <br />the last two quarters of 2007. These acres include all back filled and <br />graded areas along with buildings and asphalt areas that were approved <br />for retention through PR -3. The east end of the Conveyor Tunnel was <br />backfilled and filled with a 2 foot concrete plug. Due to inclement weather <br />and frozen soils, seeding was postponed until the 1S quarter of 2008. <br />These 13.5 acres achieved final Phase III Bond Release with SL -6 which <br />was approved on December 14, 2010. Located in the SW'/ & SE'/ <br />Section 34, Township 10 South, Range 98 West, 6 th P.M. <br />Area - 13.5 acres reclaimed <br />9.6 acres backfilled and graded <br />6.4 acres top soiled <br />Date - December 2007 <br />Seed Mix - "Seed Mix, Table 14 -8 ", Upland Components <br />Phase III Bond Release - 13.5 acres <br />