• EXHIBIT 7, ITEM 23, PART A <br />COLLOM INITIAL SEDCAD MODELING <br />Runoff from Little Collom Gulch will be treated in two facilities during the early, worst -case phase of <br />operations. One, the Little Collom Sump (also referred to as the LCX -IN in the model), is an excavated <br />sump within the Little Collom X pit, located at the bottom of the Collom syncline. The other, Little <br />Collom Pond (also referred to as the LCX -DS in the model), is an embankment dam containing slightly <br />less than 20 acre -feet of storage, and located downstream of the mine operations. It operates as a flow - <br />through pond, drained by a perforated riser and floating siphon. <br />The location of the Little Collom sedimentation ponds is presented on the included Exh. 7 -23, Figure Al. <br />Channel designs of these permanent drainage channels are provided in Exhibit 7, Item 23, Part E. Exhibit <br />7, Item 23, Figure Al shows the breakdown of drainage areas and hydrologic conditions for the two <br />sediment ponds. <br />A design drawing for the impoundments is presented on Figures 1 and 2 of Exhibit 7, Item 26. <br />The following pages present the results of three SEDCAD runs for the worst case hydrologic conditions. <br />The results of the 10, 25, and 100 year, 24 hour storms are presented. The 25 -year storm is analyzed <br />assuming a clogged principal spillway riser in LCX -DS, and a starting water surface at the emergency <br />spillway invert, to provide a conservative spillway design. Further information regarding the design <br />assumptions and the model inputs are documented in the introductory text of Exhibit 7, Item 23. <br />Parts B and C of Exhibit 7 -23 provide a summary of the design parameters for the two sediment ponds. <br />The ongoing mining activities within each watershed of the permit area will create constantly changing <br />hydrologic conditions. The design models are generally based on a static, theoretical scenario, utilizing <br />SEDCAD 4, which considers the worst -case scenario. The worst -case scenario occurs approximately 6 <br />months after the start of mining, when topsoil has been stripped and stockpiled for all of Little Collom X, <br />and portions of Collom Lite, but no mining or sedimentation control installation has yet occurred in <br />Collom Lite. Reclamation has not yet been attained for any areas. The 6 -month disturbance boundary <br />indicated in Exhibit 7 -23, Figure Al is for development of the worst -case scenario for hydrologic <br />modeling and does not represent a definitive schedule for mining and reclamation activities. After this <br />initial 6 month period, the Collom Lite pit will be sufficiently developed to contain runoff within it, <br />effectively reducing the drainage area being served. <br />• <br />Exh. 7 -23A -1 Revision Date: 12/15/10 <br />Revision No.: PR -03 <br />