amec <br />Earth & Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: November 21, 2009 <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day <br />Reporting Period: 11/15/09 through 11/21/09 <br />Days S M T W T F S <br />Work Shifts - D D D D D D- <br /> <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 20°F to 32°F (+/-) High: 36°F to 55°F (+/-) <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: Limited work activities on the morning of the 16th due to weekend snows. <br />No weather related delays during the week. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Clearing and Grubbing <br />1) VLF <br />No work performed during the week. <br />B) Stripping <br />1) VLF <br />No work performed during the week. <br />C) Subgrade Preparation <br />1) VLF <br />No work performed during the week. <br />D) Slope Contouring <br />1) VLF <br />Slope contouring was performed between stations H0+00 (+/-) and H3+00 (+/-), approximately <br />20 feet left to 20 feet right of centerline using a CAT D-9 dozer, and a CAT 345 excavator. <br />Material generated during slope contouring was pushed down slope at the cut progressed. <br />VLF Weekly Report WE 11.21.09.D.doc