ame <br />Earth & Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 Project No.: 8420125EO <br />Owner: Cripple Creek & Victor Gold Mining Co. Contractor: Ames Construction Co., Inc. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: 2/17/09 Reporting Period: 02/08/09 through 02/14/09 <br />Days S M T W T F S <br />Work Shifts - D D D D D - <br /> - - - N N N - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 12° High: 32° <br />AMEC CQA Personnel On-site through the Reporting Period (See Attachment A). <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />1. EARTHWORKS <br />A. Clear and Grubbing <br />1. VLF <br />• Ames started clearing and grubbing activities along the East Perimeter Access <br />Road at Station A22+00. Pioneer roads were started and work continued with a <br />D8 dozer and 330 excavator. <br />2. Sediment Collection Pond <br />• No Activities. <br />B. Stripping <br />1. VLF <br />• Ames continued to relocate the existing topsoil located near the northwest edge <br />of the Phase 5 VLF. The topsoil was being hauled to the lower stockpile north <br />of the five point intersection. <br />• No Activities. <br />2. Sediment Collection Pond <br />• No Activities <br />C. Waste Rock to Stockpile <br />1. VLF <br />• No Activities <br />2. Sediment Collection Pond <br />Sheet 1 of 6 <br />VLF Weekly Report WE 02.13.09.doc