Laserfiche WebLink
amecmO <br />Earth & Environmental <br />• CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. Field observation included removal of topsoil in the VLF at locations noted <br />above in the Earthworks section and transporting it to the lower topsoil stockpile north of the five point <br />intersection. Two samples of unprocessed clay were collected for laboratory testing. Samples were sent <br />to the AMEC lab for permeability testing. The sample numbers were SLF-1-C and SLF-2-C. One sample <br />of the processed clay was collected and shipped to the AMEC lab for testing (SLF-3-C). <br />No night shift work was performed during the week. <br />No work was performed on Saturday, January 31. Currently no work activities are planned for Saturdays <br />but Ames has indicated that Saturday will be used as a make up day in the event of delay or stoppage <br />during the current planned work periods Monday to Friday. <br />Testing Summary <br />No testing was performed at this time. <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />• None noted. <br />Summary of Non-conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC& V. <br />Ames Construction: <br />Amec: <br />Others: <br />Daily Safety/Tailgate Meetings: <br />AMEC staff attended the daily tailgate safety meeting this week. <br />Summary of Incidents/Accidents/Health & Safety Issues <br />None noted. <br />• CQA Monitor: Alfonso Frias Date: 02/03/09 <br />Approved By: Date: <br />Sheet 3 of 4 VLF Weekly Report WE 01.31.09.D.doc