<br /> <br />ame& <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: October 23, 2010 <br />Reporting Period: 10/17/10 through 10/23/10 <br />Days S M T W T F S <br />Work Shifts D D D D D D D <br /> - - N N N N N <br />D = Day Shift N = Night Shift <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day/Night <br />Ambient Temperature Range (F): Low: 47°F to 64°F (+/-) High: 34°F to 37°F (+/-) <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: Night shift began for ore placement within the Phase 5 PSSA on 10/19/2010. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />I) EARTHWORKS <br />A) Subgrade Preparation <br />1) VLF <br />Subgrade was inspected and approved for soil liner fill placement by an AMEC field <br />representative in the area shown on Figure 1. <br />B) Slope Contouring <br />1) VLF <br />Slope contouring was performed between stations A54+00 (+/-) and 60+00 (+/-), <br />approximately 0 to 100 feet left of centerline using various CAT dozers. <br />C) Cut to Fill <br />1) VLF <br />Fill material was placed between stations C5+00 (+/-) and C5+25 (+/-), approximately 0 to 20 <br />feet right of centerline using a CAT D8 dozer and a 10-ton vibratory smooth drum compactor. <br />This was performed to allow for access around the low volume solution collections riser pump <br />house. <br />VLF Weekly Report WE 10.23.10.13