Laserfiche WebLink
flow to the Site 114 pump by means of the existing ditches and culverts. A short temporary ditch may need to be <br />inscribed from the PM road culvert to Site 114 in order to route the flow to the pump. When no longer required, the <br />• overland line will be disconnected allowing the 109 discharge to again flow to Pond D, and the temporary ditch will be <br />removed. <br />A pumphouse was constructed at Pond A to supply water to the coal preparation plant. The pumphouse is an <br />approximately 15 x15 foot metal building on a concrete slab. The building contains the pumps and associated controls. <br />The water is pumped through a new 8 -inch waterline buried along the shoulder of the existing access road from the <br />Tipple to Pond A. The waterline runs from Pond A to a new valve box at Location A. The buried waterline continues <br />to a new valve box at Location B. The new line then continues adjacent to Haul Road B to existing Location 8 and on <br />to new Location C. New waterlines were laid from Location C into the preparation plant and to existing Location 6. <br />The location of the new waterlines and valve boxes are shown on Map 24, Surface Facilities. All new waterlines will <br />be located within existing disturbed areas. <br />Pumphouse Addition (MR06 -205) <br />The existing pumping system delivering water from the TCC million- gallon tank to the underground operations <br />would not meet anticipated water requirements for the new longwall. To meet increased water delivery <br />requirements, TCC installed two 150 -HP, 480 -Volt, variable frequency drive (VFD) pumps. The dual -pump <br />system provides peaking capacity and allows one pump to serve as a backup, under normal operational conditions. <br />The pad for the Pumphouse is in a previously disturbed area, but required some fill placement and grading to <br />establish a stable foundation. The pad footprint was over excavated, and suitable fill material was placed and <br />compacted to one -foot below grade. The Pumphouse foundation is a 6 -inch thick reinforced slab with the footings <br />extending approximately 4 feet deep. Following foundation excavation and construction, six inches of 3 / - inch <br />gravel was placed on pad areas adjacent to the foundation slab. The foundation slab includes two reinforced <br />• concrete piers extending approximately one -foot above the slab surface to support and isolate the pump and drive <br />assemblies. A 20 x 17 foot insulated pre- fabricated steel building was erected adjacent to the existing Electric Shop <br />to accommodate the two VFD pump skids and drives, a heating and ventilation system, and provide for <br />maintenance access. Three new powerpoles and a short connector line connect the pump installation to the existing <br />Substation No. 7. Piping from the new pumping installation connects to the three existing underground water lines <br />(suction, pressure, and recirculation) that run adjacent to the existing Electrical Shop. Design drawings and <br />construction specifications for the Pumphouse foundation and building are provided in Exhibit 49F, and the <br />Pumphouse location is shown on Map 24 (Sheet 1 of 3), Surface Facilities and Freshwater Systems. <br />As part of the mine surface facilities, the Pumphouse addition will be reclaimed in conjunction with final <br />reclamation of the mine facilities area, as described under the sub - heading "Surface Facilities" on page 2.05 -101 of <br />the PAP. In general, this will involve removal of the two pump and drive assemblies along with associated surface <br />piping (existing buried piping to be stubbed -off and abandoned in place); demolition and disposal of the <br />Pumphouse building, foundations, and powerline and poles. The pad area will be regraded to reestablish effective <br />drainage and blend with the surrounding terrain. Stockpiled topsoil will then be replaced and seeded with a <br />pastureland seed mixture. <br />Washplant II Waterline and Connection (TR07 -59, Washplant 111) <br />In order to supply adequate water to Washplant II, a new 10,000 -foot, 6 -inch HDPE waterline will be installed between <br />Washplant H and the Area 1 Pit. A 5 -6 foot deep trench will be excavated from the Area 1 Pit to the Washplant H <br />location, adjacent to or in the same location as the existing 4 -inch waterline. Since the trench will fall entirely within a <br />previously disturbed area, no topsoil remains and no soil salvage will be required. Once the waterline is laid in the <br />trench and properly bedded, the trench will be backfilled and the material compacted. An additional pump will be <br />• placed in the Area 1 Pit and connected to the new waterline. Either a float or submersible pump will be utilized, with <br />pump control and access from the existing pump- station access in the Area 1 Pit. In addition, a short buried 8 -inch <br />HDPE connector line will be extended from the Washplant II water supply line to the existing 8 -inch waterline that now <br />runs between Pond A and the existing Washplant I, to provide an alternate /supplemental water supply for Washplant H. <br />A manhole with manual valves or automated control valves will be used to control flow to the Washplant. <br />MR09 -238 2.05 -53 06/26/09 <br />