amecs <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day/Night <br />Work Element: Phase 5 CQA/ VLF <br />Date: August 14, 2010 <br />Reporting Period: 8/8/10 through 8/14/10 <br />Days S M T W T F S <br />Work Shifts D D D D D D D <br /> - N N N N N - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 50°F to 54°F (+/-) High: 66°F to 82°F (+/-) <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: Afternoon rain showers delayed work activities periodically during the week. Due to <br />heavy rainfall, erosion of the Phase 5 VLF east slope was observed. Sediment reported to the <br />bottom of the Phase 5 PSSA. Ames continued remediation and installation of temporary erosion <br />controls. <br />AMEC was informed by Ames that nightshift would be finished Friday, 8/13/2010. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Subgrade Preparation <br />1) VLF <br />No work performed during the week (see Figure 1 for previous subgrade acceptance). <br />B) Slope Contouring <br />1) VLF <br />No work performed during the week. <br />C) Cut to Fill <br />1) VLF <br />No work performed during the week. <br />VLF Weekly Report WE 08.14.10.1)