Colowyo's Response: <br />Colowyo will submit a technical revision to the Division reflecting the slow down in the <br />progression of the West Pit by October of 2010. As Colowyo is currently moving through <br />the budget planning phase for the subsequent years of 2011 and 2012 and allocating <br />manpower, equipment hours, resolving coal quality and sequencing issues, a more rapid <br />submittal course would result in the need to modem the map yet again. Colowyo concedes <br />this is an issue that warrants attention, but the benefit gained by waiting until budget <br />considerations are resolved in the short term will be worth the wait by requiring fewer <br />updates moving forward. <br />2. Colowyo shows highwall mining of the E2-Seam in the South Taylor Pit from 2009-2012. <br />Colowyo completed highwall mining in the area under the East Taylor Fill in 2009. <br />Please advise the Division whether additional highwall mining is proposed for this area, as <br />indicated on Map 23A - Mine Plan South Taylor Area. If no additional highwall mining <br />is planned for this area, please update Map 23A to indicate that all highwall mining for <br />this area was completed in 2009. <br />Colowyo's Response: <br />It is undecided at this time if and when additional highwall mining activities will continue <br />in the South Taylor area. Colowyo reserves the right to keep these potential highwall <br />mining areas on Map 23A. If a permanent change is made prior to 2012 confirming that <br />no additional highwall mining activities will take place, Colowyo will, at such time, submit <br />a technical revision revising the South Taylor mine plan on Map 23A of its permit. <br />Colowyo is aware that additional information will need to be submitted and approved <br />prior to the commencement of highwall mining activities in the South Taylor area for <br />certain locations and will follow this established process. <br />3. If necessary, based on the progression of the South Taylor Pit, please update the highwall <br />mining dates for the area that is proposed for highwall mining under the West Taylor Fill <br />(2009-2012). Please note that specific approval for highwall mining in this area has not <br />been granted and, prior to performing any highwall mining in this area, Colowyo must <br />submit and have approved a technical revision specific to this area. <br />Colowyo's Response: <br />See response to comment #2. <br />4. There is text on Page 2.05-18 describing the Section 16 Pit and West Pit in the future tense <br />(the pits will be developed). Since mining has been completed in the Section 16 Pit and <br />nears completion in the West Pit, please update this text to discuss these pits in the present <br />or past tense, as necessary. Colowyo may wish to keep some of the historical information <br />describing the permitting of these pits but the remaining text needs to describe the pits as <br />they are currently. <br />Colowyo's Response: <br />Colowyo will submit a minor revision by the end of August, 2010 to address this issue. <br />5. On page 2.05-19 Colowyo presents a chart of projected excess spoil as of 31 December <br />2006. This chart shows a balance of total excess spoil for the Streeter Fill, Section 16 Fill <br />and West Pit Fill. Since these fills have been completed (with only the removal of Hink's <br />Peak and final reclamation of the West Pit Fill remaining), please update this chart to <br />show the volumes of excess spoil that went into each fill as well as the total excess spoil