2.05.3 <br />2) Haul Road along old railroad bed. <br />General Requirements <br />This road has two segments. One is approximately 3,000 feet long and <br />provides access to Gob Pile #1. The second segment turns off of segment <br />one at station 123 +00 and is approximately 300 -feet long to provide access <br />to Gob Pile No. 2. Reference Map 16, Haul Road Plan & Profile - Gob Pile. <br />These roads provide access to the gob piles and sediment ponds C, D and <br />F. Drainage from the majority of the road is not contained in any sediment <br />ponds. A portion of this road was re- constructed with the preparation plant <br />construction project. Excess fill from the preparation plant site work was be <br />placed along this road segment. <br />Dust control on this road segment includes gravel surfacing and watering to <br />maintain surface moisture. <br />Alternative sediment control will be utilized to assure that erosion, siltation, <br />pollution of air or water, and damage to public property will be controlled. <br />The use of dust and alternative sediment control will assure that no damage <br />to fish and wildlife or other related environmental values will occur. <br />• <br />The truck traffic which will utilize this haul road segment will be 10 wheel haul <br />trucks and 35 to 50 ton haul trucks. Considering the light traffic anticipated, <br />a 20 -foot wide road surface should be adequate for these haul trucks. <br />Vehicle traffic should have no problem with this road configuration. About <br />300 -feet of segment one has an 11% grade, from Stations 126 +00 to <br />126 +00. No other area of either haul road segment exceeds 10% grade. <br />Design and Construction <br />For the construction of this road segment, all vegetation material and topsoil <br />will be removed from the design road bed, shoulders, and surfaces where <br />associated structures will be placed. Topsoil will be placed in one of the <br />topsoil stockpiles located on site. No vegetation material or topsoil will be <br />placed beneath or in any haul road embankment. <br />The embankment specification presented above applies to this road <br />segment. <br />Drainage <br />The discussion of drainage presented above under the discussion of the <br />main haul road is applicable to this road segment except drainage from this <br />road segment does not pass through a sediment pond. Drainage from this <br />TR -30 2.05-22- 11/03 <br />/3 Pf ROUC lD <br />3/z3/d y <br />