amec <br />Earth & Environmental <br />V) VLF Geosynthetics <br />Three loads of 100mi1 LLDPE geomembrane were delivered to site during the week for a total of 33 <br />rolls. All loads were delivered on flat bed trucks in good condition. The rolls were unloaded using a <br />CAT 966 front-end loader with forks attached. The geomembrane was placed on three pieces of 4" <br />HDPE pipe, staked two rolls high. An AMEC field representative was present at all times during <br />unloading of the geomembrane. The AMEC representative also inventoried the geomembrane, as it <br />was unloaded. <br />The Phase IV geomembrane was exposed between stations G10+00 (+/-) and G29+00 (+/-), <br />approximately 150 feet left of centerline using a John Deere 35D excavator and two laborers. This was <br />performed in order prepare for the tie-in. An AMEC field representative was present at all times <br />during geomembrane exposure. <br />Anchor trench excavation began between stations F0+00 (+/-) and F5+00 (+/-), approximately 5 feet <br />right of centerline using a John Deere 35D excavator. AMEC inspected the trench periodically though <br />out the week. The trench was found to be constructed properly. <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed structural fill placement within the Phase 5 VLF fill area. Ambient temperatures were <br />monitored during fill placement. <br />AMEC inspected and approved subgrade for SLF placement within the Phase 5 VLF. <br />AMEC observed, obtained moisture samples, and assisted in the placement of SLF material within the <br />Phase 5 VLF. <br />AMEC observed, obtained samples, and assisted in the process of SLF material at the East Cresson Clay <br />Borrow. <br />AMEC observed, obtained samples, and assisted in the process of LVSCF at Pad 4 <br />AMEC observed and inventoried geomembrane delivered from Polyflex to site. <br />AMEC observed the exposure of the Phase IV geomembrane constantly. <br />Testing Summary <br />Laboratory testing continued (Particle Size Distribution, Atterberg Limits, Moisture-Density Relations, <br />Specific Gravity, Permeability, and Point Load testing) for sampled materials. <br />VLF Weekly Report WE 05.15.10.D