Article 43. STATE'S RIGHTS TO TERMINATE THE CONTRACT <br /> A. General <br /> If the Contractor should be adjudged a bankrupt,or if he should make a general assignment for the benefit <br /> of his creditors,or if a receiver should be appointed to take over his affairs, or if he should fail to prosecute <br /> his work with due diligence and carry the work forward in accordance with his work schedule and the time <br /> limits set forth in the Contract Documents, or if he should fail to subsequently perform one or more of the <br /> provisions of the Contract Documents to be performed by him, the.Principal Representative may serve <br /> Written Notice on the Contractor and the Surety on his performance and payment bonds,stating his intention <br /> to exercise one of the remedies hereinafter set forth and the grounds upon which the Principal <br /> Representative bases his right to exercise such remedy. In such event, unless the matter complained of <br /> is satisfactorily cleared within ten (10) days after serving such Notice, the Principal Representative may, <br /> without prejudice to any other right or remedy, exercise one of such remedies, at once. <br /> B. Conditions and Procedures <br /> (a) The Principal Representative may terminate the services of the Contractor,which termination shall <br /> take effect immediately upon serving notice to the Contractor and his Surety,whereupon the Surety <br /> shall have the right to take over and perform the Contract. If the Surety does not commence <br /> performance of the Contract within ten (10) days after service of the notice of termination, the <br /> Principal Representative may take over the work,take possession of and use all materials,tools, <br /> equipment and appliances on the premises and prosecute the work to completion by such means <br /> as he shall deem best. In the event of such termination of his service,the Contractor shall not be <br /> entitled to any further payment under his.contract until the work is completed and accepted. If the <br /> Principal Representative takes over the work and if the unpaid balance of the contract price exceeds <br /> the cost of completing the work, including compensation for any damages or expenses incurred by <br /> the Principal Representative through the default of the Contractor, such excess shall be paid to the <br /> Contractor. If, however, the cost, expenses and damages as certified by the Principle <br /> Representative exceed such unpaid balance of the contract price,the Contractor and his Surety <br /> shall pay the difference to the Principal Representative. <br /> (b) The Principal Representative may take control of the work and either make good the deficiencies <br /> of the Contractor or direct the activities of the Contractor in doing so,employing such additional help <br /> as the Principal Representative deems advisable. In such event the Principal Representative shall <br /> be entitled to collect from the Contractor and his Surety, or to deduct from any payment then or <br /> thereafter due the Contractor,the costs incurred in having such deficiencies made good and any <br /> damages or expenses incurred through the default of the Contractor, provided the Principle <br /> Representative approves the amount thus charged to the Contractor. <br /> (c) The Principal Representative may require the Surety on the Contractor's bond to take control of the <br /> work at once and see to it that all the deficiencies of.the Contractor are made good, with due <br /> diligence. As between the Principal Representative and the Surety,the cost of making good such <br /> deficiencies shall all be bome by the Surety. If the Surety takes over the work, either upon <br /> termination of the services of the Contractor or upon instructions from the principal Representative <br /> to do so,the provisions of the Contract Documents shall govern in respect of the work done by the <br /> Surety,the Surety being substituted for the Contractor as to such provisions, including provisions <br /> as to payment for the work and provisions of this Article as to the right of the Principal <br /> Representative to do the work or to take control of the work. <br /> Colorado Division of Minerals&Geology GENERAL BID SPECIFICATIONS <br /> 1996 Page 15 <br />