• 14.0 Construction Schedule <br />Construction of the ore storage pads will occur following approval of the design from <br />DRMS and prior to ore production. Surface preparation at each ore storage pad area <br />will be completed, followed by the installation of the PVC geomembrane, then <br />backfill. Denison will notify DRMS in writing 10 working days prior to construction so <br />that a pre-construction inspection can be conducted and, if need be, construction <br />oversight scheduled. It is anticipated that the construction timeframe to complete all <br />ore storage pads will be less than two months upon commencement of these activities. <br />Following construction of each of the ore pads, Denison will provide DBMS with <br />certification by a professional engineer or other appropriately qualified professional <br />that will confirm that the facilities have been constructed in accordance with the <br />approved design. <br />• <br />• <br />14-1 <br />T:W49884)enison Wnes\Task Order 4 - EPP Sunday Mines Gimp-VanASunday Mrt Gwap1DRMS RTC (Round 2) and Revised EPPIPINAL ORMS Repod RTCv2 - EPP Sunday Knead=