i 14.0 Construction Schedule <br />Construction of the ore storage pad will occur following approval of the design from <br />DRMS and prior to ore production. Surface preparation at the ore storage pad area <br />will be completed, followed by the installation of the PVC geomembrane, then <br />backfill. Denison will notify DRMS in writing 10 working days prior to construction so <br />that a pre-construction inspection can be conducted and, if need be, construction <br />oversight scheduled. It is anticipated that the construction timeframe to complete the <br />ore storage pad will be less than two months upon commencement of these activities. <br />Following construction of the ore pad, Denison will provide DRMS with certification <br />by a professional engineer or other appropriately qualified professional that will <br />confirm that the facility has been constructed in accordance with the approved design <br />plan. <br /> <br />0 <br />141 <br />T %49884erB Gfn %Task Order 4 - EPP &AX* Mtr GMup VaMNan4VRMS RTC (Rand 2) and WvMd EPP1FBiAL DRMS Report - EPP Van4Aa: