2009 Hole Plugging <br />All plugging activities were overseen by Blue Mountain Energy, Inc. Engineering Dept. staff. <br />Return Shaft #3 (RS-3) <br />On November 1, 2009 RS-3 was permanently sealed by backfilling from the bottom to the surface with <br />soil previously stockpiled on site. Cook's Trucking provided the equipment and operators to perform <br />this task. The portion of the steel liner projecting above the surface was then cut flush with the <br />concrete pad and a 6+ inch concrete plug was poured on the top. <br />LWB9-2, LWB9-3, SC-TG29, SC-HG26, and the 11" open borehole adjacent to RS-4 <br />In November 2009 these holes were completely backfilled with concrete directly from cement trucks. <br />The bottoms of SC-TG29 and SC-HG26 were first plugged by dropping long capped steel pipes to the <br />mine floor to prevent the concrete from pouring into the mine. A thicker aggregate mix was then placed <br />down the hole to complete the bottom plug prior to backfilling with cement. <br />The 11" open borehole adjacent to RS-4 was also backfilled with cement. This hole initially bridged off <br />at approximately 300 feet. Four bags of concrete were poured down the hole to ensure a competent <br />bottom plug. The remainder of the hole was backfilled with cement directly from cement trucks. <br />SC-SL1, SC-HG54, SC-HG44-2 and SC-TG33 <br />These holes were initially constructed without plugging the outside annuluses of the pipes with cement. <br />In November 2009 the inside casings to the mine were plugged by placing obstructions in the casings at <br />over 20 feet and placing %2 bag of concrete mix on top to form an initial seal. The inside casings were <br />then lifted from their support structures and lowered to the mine floor if they were still free hanging. <br />The inside annulus of the surface casings, outside annulus of the inside casings (portions still open) and <br />remaining upper inside annulus were backfilled with cement directly from cement trucks. <br />SC-HG11, SC-HG20, SC-HG33, SC-HG56, SC-TG56, SC-HG59, LWB7-1 <br />The outside annulus of the steel casing was cemented from the mine to the surface during initial <br />construction of these holes. The inside pipes to the mine were plugged in November 2009 by placing <br />obstructions in the pipes at over 20 feet and placing %2 bag of concrete mix on top to form an initial seal. <br />The remainder of the upper annulus was filled with cement once the initial concrete had adequately set <br />to provide structural support for the cement.