CIRCES Cost EstimatinaSoftware
<br />DEMOLITION WORK
<br />STRUCTURE or ITEM DESCRIPTION DIMENSIONS DEMOLITION MENU SELECTION QUANTITY UNIT UNIT COST TOTAL COST
<br />-Mine office superstructure 20'x 65'x 18' Demo./disp./appr dump - to 5 mi. 23,840.00 CF $0.6443 $15,359.69
<br />-Mine office slab 4"x 2980 s.f. Floor, concr, avg. reinf. - 4'th. 2,980.00 SF $1.1147 $3,321.94
<br />-haul mine office concrete NA Load15 mi. haul, slvg. - Concr. fr. 200.00 CY $8.6800 $1,736.00
<br />-Mitre office footing V x 2'x 220' Footing, concrete - 1.0'D x 2'W 220.00 LF $6.6885 $1,471.46
<br />Bridge - WA /eft in place
<br />-Shop superstructure 60'x 40'x 14' Demo./disp./existing pd - 200' push 33, 600.00 CF $0.1295 $4,350.56
<br />-shop floor 60'x40' Demo./disp. exs. p8, 8'th.-50 ft. 2,400.00 SF $2.2427 $5,382.58
<br />
<br />-Warehouse #1 structure 100'x 75'x 20' Demo./disp./existing pit - 200' push 150,000.00 CF $0.1295 $19,422.13
<br />-floor 40'c 80' Demo./disp. exs. pit, 8"th.- 50 ft. 3,200.00 SF $2.2427 $7,176.77
<br />-footing 1.5'x 3'x 350' Demoldisp.exs.pit, 1.5'x3=50 ft. 350.00 LF $15.1385 $5,298.48
<br />
<br />-Warehouse #2 structure 45'x 24'x 9' Demo./disp./exisfing pit - 200' push 9,720.00 CF $0.1295 $1,258.55
<br />-floor 45'x24' Demo./disp. exs. pit, 6'th.-50 ft. 1,080.00 SF $1.6821 $1,816.62
<br />
<br />-Ventilation Fan 15'x 10'x 8' Demo./disp./existing pit - 200' push 1,200.00 CF $0.1295 $155.38
<br />-pad 15'x 10' Demo./disp. exs. pd, 12" th.- 50 ft. 150.00 SF $3.3641 $504.62
<br />
<br />-Substation structure 12'x 12'x 15' Demo./disp./existing pit - 200' push 2,160.00 CF $0.1295 $279.68
<br />-pads 12'x 12' Demo./disp. exs. pit, 4'th.- 50 ft. 144.00 SF $1.1214 $161.48
<br />-Transformers behind shop 6'x 6'x 6' Demo./disp./existing pit - 200' push 216.00 CF $0.1295 $27.97
<br />-pad 6'x 6' Demo./disp. exs. pit, 6" th.- 50 ft. 36.00 SF $1.6821 $60.55
<br />
<br />-Powerines 1,4001in.ft. PoweNphoneline - single pole 1,400.00 LF $2.4700 $3,458.00
<br />conveyor 25' inside portal 25'x 6'x 5' Conveyor, ovedand - 5'W x 6'H 25.00 LF $14.7500 $368.75
<br />-conveyor portal to stacking tube 300'x 6'x 8' Conveyor, elevated - 5' W x 6'H 300.00 LF $36.8500 S11,055.00
<br />-conveyor recl.tunnel toload bin 265'x6'x8' Conveyor, overland -5'Wx 6'H 265.00 LF $14.7500 $3,908.75
<br />-conveyor support/retaining wall at bench 12'x 10'x 35' Demo./disp. exs. pit, 12'th.- 50 ft. 350.00 SF $3.7036 $1,296.28
<br />
<br />-stacking tube 6' diam x 60' Pipe, CMP - 72 in. diam. 60.00 LF $51.9175 $3,115.05
<br />-reclaim tunnel 8' diam x 75' Pipe, CMP - 96 in. diam. 75.00 LF $90.3988 $6,779.91
<br />
<br />-Loading bin structure 20'x 20'x 30' Demo./disp./existing pit - 200' push 12, 000.00 CF $0.1295 $1,553.77
<br />-footing V x 2'x 40' Footing, concrete - 1.0' D x 2' W 40.00 LF $6.6885 $267.54
<br />
<br />-debris removal 500- - - Load15 mi: haul, slvg: - Steel fr- 500.00 Cy $73600- - - $3,680.00. -
<br />-surface tanks 2-500,1-250 Demo./disp./appr dump - to 5 mi. 147.00 CF $0.6443 $94.71
<br />-sludge removal 10% volume Remove contents - 3K- 5K gal. 1.00 EA $156.5000 $156.50
<br />-industrial chemicals 5 drums Haz. waste - Drum mat., 1-6 dr. 5.00 DRUM $397.5609 $1,987.80
<br />-water tank 6k gal, 8.48 d/g Demo./disp./appr. dump - to 5 mi. 708.00 CF $0.6443 $456.15
<br />-tank pad 10' diam Floor, Concr, avg- reinf. - 6" th. 79.00 SF $1.6721 $132.10
<br />-pad disposal 1.5 cu. yds Load15 mi. haul, s1vg. - Concr. fr. 1.50 CY $8.6800 $13.02
<br />-septic tank NA Exc./load, non-leaking-3K- 5Kgal. 1.00 EA $406.5000 $406.50
<br />-remove sludge from tank NA Remove contents - 3K- 5K gal. 1.00 EA $156.5000 $156.50
<br />-disposal of sludge NA OH-site sludge disposal - Avg. 100.00 GAL $3.5300 $353.00
<br />-TR 12 screen addition 5'x 8'x 8' Demo./disp./existing pit - 200' push 320.00 CF $0.1295 $41.43
<br />conveyors to screen 2-40', 1-80' Conveyor, overland - 5'W x 6'H 140.00 LF $14.7500 $2,065.00
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />JOB COST Subtotal (unadjusted): $109,130 Total Cost (adjusted for location): $100,748
|