ame& <br />H. Drain Cover Fill <br />1. Drain Cover Fill shall be placed over the geomembrane in the locations shown on the <br />DRAWINGS. <br />2. Prior to placing the Drain Cover Fill, CONTRACTOR shall verify by visual inspection that <br />the underlying geosynthetics are free of holes, tears, wrinkles, or foreign objects. <br />MANAGER and CERTIFYING ENGINEER will inspect the geosynthetic for wrinkles <br />prior to placement of Drain Cover Fill. As instructed by MANAGER, CONTRACTOR <br />shall "work out" wrinkles to the satisfaction of MANAGER and CERTIFYING <br />ENGINEER prior to placement of the Drain Cover Fill. In all cases, wrinkles shall not be <br />of a size that they could fold back on themselves. Wrinkles greater than one foot shall be <br />removed and repaired by the INSTALLER. <br />CONTRACTOR shall place Drain Cover Fill in a single 24 -inch loose lift. The tracked <br />equipment shall operate only over previously placed Drain Cover Fill. CONTRACTOR <br />shall not operate equipment directly on geosynthetics. Only a dozer with a ground pressure <br />not exceeding 8.7 psi can be used to place Drain Cover Fill. A CAT 12G motor grader, or <br />equivalent approved by CERTIFYING ENGINEER, can be used for Drain Cover Fill final <br />grading. Equipment used for placement will not be allowed to pivot on one track (i.e., no <br />abrupt or sharp turns). There shall be no downhill placement on slopes steeper than 4H: IV. <br />Material can be placed along contours if buttressed from below. Motor graders shall not be <br />allowed to make abrupt turns, brake suddenly, or dig blade in which results in the tires <br />spinning on the Drain Cover Fill surface. <br />4. Highway compatible Rubber tired construction equipment shall not be allowed to travel over <br />the geomembrane or on top of Solution Collection piping unless a thickness of at least 45 <br />inches of Drain Cover Fill has been placed over the geomembrane and on top of Solution <br />Collection piping. The CONTRACTOR will be required to demonstrate to the <br />MANAGER, DESIGN ENGINEER and CERTIFYING ENGINEER that the equipment <br />and procedures used are not detrimental to the geomembrane and piping, at no cost to <br />CC &V. Off road haul truck traffic shall require a minimum of 60 inches for Cat 773 (or <br />equivalent) of Drain Cover Fill placed over the geomembrane and solution collection piping, <br />and a minimum of 120 inches for CAT 777 (or equivalent) of Drain Cover Fill placed over <br />the geomembrane and solution collection piping. <br />When placing Drain Cover Fill the maximum acceptable drop height is 3 feet. <br />6. CONTRACTOR shall operate equipment in a manner that is protective of underlying <br />geosynthetics. If MANAGER or CERTIFYING ENGINEER suspects the occurrence of <br />any damage to the underlying geosynthetics, MANAGER will instruct CONTRACTOR to <br />remove Drain Cover Fill to expose the geosynthetics. CONTRACTOR shall uncover, <br />repair any observed damage of the underlying geosynthetics, in accordance with the repair <br />requirements of Sections 02776.0 and 02777.0 of these SPECIFICATIONS, and recover, at <br />no cost to CC &V. <br />7. CONTRACTOR shall place Drain Cover Fill at a rate such that the geomembrane liner is <br />not exposed to ultraviolet light for more than 180 days. <br />8. CONTRACTOR shall provide close continuous monitoring at the point of placement <br />during the placement of the Drain Cover Fill over geosynthetics. <br />Section 02200 Page 15 of 18 September 3, 2008 <br />Earthworks Revision 1 <br />SAProjects \1125E CCV CQA \I - Tech Specs \02200.rt.doc <br />