geosynthetics, in accordance with the repair requirements of Sections 02776.0 and 02777.0 <br />of these SPECIFICATIONS, and recover, at no cost to CC &V. <br />9. CONTRACTOR shall place Low Volume Solution Collection Fill at a rate such that no <br />single area of 350,000 square feet of geomembrane liner is exposed to ultraviolet light for <br />more than 180 days. <br />10. CONTRACTOR shall provide close continuous monitoring at the point of placement <br />during the placement of the Low Volume Solution Collection Fill over geosynthetics. <br />11. CONTRACTOR shall verify the final thickness of Low Volume Solution Collection Fill to <br />determine compliance with this SPECIFICATION. CONTRACTOR shall record <br />verification location, elevation, and thickness. CQA Monitor shall wilness all verification <br />measurements. CONTRACTOR will submit a method of verifying Low Volume Solution <br />Collection Fill depth to MANAGER for approval. Grade markers shall be placed on a 50- <br />by -50 -foot grid with additional points required for breaks in grade. CONTRACTOR shall <br />remove all grade markers under supervision of CQA Monitor after verification <br />measurements have been approved by MANAGER and CERTIFYING ENGINEER and <br />will backfill holes with Low Volume Solution Collection Fill. Areas with deficient thickness <br />shall be reworked by CONTRACTOR, until acceptable measurements are obtained. If <br />MANAGER or CERTIFYING ENGINEER suspects the occurrence of any damage to the <br />underlying geosynthetics, MANAGER will instruct CONTRACTOR to remove Low <br />Volume Solution Collection Fill to expose the geosynthetics. CONTRACTOR shall <br />uncover, repair any observed damage of the underlying geosynthetics, in accordance with <br />• the repair requirements of Sections 02776.0 and 02777.0 of these SPECIFICATIONS and <br />recover, at no cost to CC &V. <br />12. CONTRACTOR will provide adequate illumination as approved by MANAGER, if Low <br />Volume Solution Collection Fill placement is carried out at night. A minimum of 2 -foot <br />candles measured at the synthetic liner, shall be used when Low Volume Solution Collection <br />Fill placement is carried out at night. <br />G. Soil Liner Fill <br />1. Soil Liner Fill shall be placed within the limits of the valley leach facility as shown on the <br />DRAWINGS and shall begin only after completion of all, or MANAGER and <br />CERTIFYING ENGINEER approved portion of, excavation and Structural Fill placement <br />in the valley leach facility. <br />2. CONTRACTOR shall process, place and compact the Soil Liner Fill to achieve a <br />coefficient of permeability of less than 1x10 -6 cm/sec, measured according to ASTM <br />Method D5084, Method D. Any Soil Liner Fill not meeting the permeability specification <br />shall be removed and replaced with material meeting the permeability specification, at no <br />additional cost to CC &V. <br />3. CONTRACTOR shall place and compact the Soil Liner Fill in loose lifts such that the <br />compacted lift thickness is a minimum of 12- inches. <br />4. CONTRACTOR shall compact the Soil Liner Fill to at least 95 percent of the maximum <br />dry density as determined by the Standard Proctor density test (ASTM D698). The moisture <br />49 content shall be within +3% to -2% of the optimum moisture content. Both moisture and <br />density shall be uniform throughout the lift. If the Soil Liner Fill cannot be conditioned to <br />Section 02200 Page 12 of 18 September 3, 2008 <br />Earthworks Revision 1 <br />S: \Projects \1125E CCV CQA \I - Tech Specs \02200.r1.doc <br />