2009-11-24_REPORT - M1980244
DRMS
>
Day Forward
>
Report
>
Minerals
>
M1980244
>
2009-11-24_REPORT - M1980244
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/15/2021 5:52:23 PM
Creation date
11/30/2009 7:30:55 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
REPORT
Doc Date
11/24/2009
Doc Name
Weekly Construction Quality Assurance ("CQA") Reports: 10/25/09 and 11/01/09
From
CC&V
To
DRMS
Type & Sequence
AM9
Email Name
BMK
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
18
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
amen <br />Earth 8 Environmental <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed placement of structural fill within the Phase 5 VLF fill area. <br />AMEC observed structural fill placement (processed ore) within the Phase IV VLF constantly. Nuclear <br />density testing was performed during placement. <br />AMEC observed the Phase IV geomembrane exposure constantly. <br />AMEC observed construction of the ADR waterline. <br />Testing Summary <br />Laboratory testing continues (Particle Size Distribution, Atterberg Limits, and Moisture- Density <br />Compaction testing) for sampled materials. <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />No concerns <br />Summary of Planning Items: <br />Structural fill placement within the Phase 5 VLF footprint will continue. <br />Continue processing soil liner fill at the South Cresson Clay Processing area. <br />Continue subgrade preparation within the Phase 5 VLF footprint. <br />Continue construction of the ADR and Crusher waterlines. <br />Continue exposure of the Phase IV VLF geomembrane for re- certification. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC& V. <br />CC &V held a Weekly Construction meeting on October 27, 2009. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />Daily Safety /Tailgate Meetings: AMEC personnel attended the Ames daily safety meeting held prior to <br />the start of shift. Discussions centered on safety and planned work activities. <br />AMEC: <br />Spoke with John Lupo concerning the design issues with the Crushing /Sediment pond culvert (42 ") and <br />the recertification at the old LOB site. John is currently working on the design issues. <br />VLF Weekly Report WE 10.31.09.D.doc <br />